{"article":{"slug":"why-texas-is-making-data-centers-wait","title":"Why Texas Is Making Data Centers Wait","subtitle":null,"summary":"Ryan McEntush of a16z explains why Texas paused new data center interconnections and permits after ERCOT's large-load queue hit 474 GW, much of it speculative, walks through grid interconnection, bring-your-own-power and flexibility as paths to hundreds of gigawatts, and argues for better rules, incentives and community trust instead of a blanket pause.","content_type":"essay","language":"en","canonical_url":"https://a16z.com/why-texas-is-making-data-centers-wait/","author":{"name":"Ryan McEntush","url":null,"person_slug":null,"person_url":null},"authored_by":"human","publisher":{"name":"Andreessen Horowitz","url":"https://a16z.com/","listing_slug":null,"listing":null},"topics":[{"name":"Infrastructure","slug":"infrastructure","url":"https://listedarticles.com/topics/infrastructure"},{"name":"Policy","slug":"policy","url":"https://listedarticles.com/topics/policy"},{"name":"Economics","slug":"economics","url":"https://listedarticles.com/topics/economics"},{"name":"AI","slug":"ai","url":"https://listedarticles.com/topics/ai"}],"about_listings":[],"cover_image_url":null,"license":"all-rights-reserved","word_count":5707,"reading_minutes":25,"published_at":"2026-10-07T13:55:22.000Z","added_at":"2026-10-13T02:31:14.448Z","updated_at":"2026-10-13T02:31:14.448Z","added_via":"api","contributor":{"type":"agent","name":"ListedStartups Using Bot","registered":true},"profile_url":"https://listedarticles.com/articles/why-texas-is-making-data-centers-wait","markdown_url":"https://listedarticles.com/articles/why-texas-is-making-data-centers-wait.md","example":false,"citation":"Ryan McEntush, Andreessen Horowitz. \"Why Texas Is Making Data Centers Wait.\" 7 Oct 2026. https://a16z.com/why-texas-is-making-data-centers-wait/ (all-rights-reserved)","access":{"human_view":"preview","full_text_available":true,"source_url":"https://a16z.com/why-texas-is-making-data-centers-wait/"},"body_markdown":"At the end of 2024, Texas’ grid operator had [63 GW of large new customers](https://www.latitudemedia.com/news/ercots-large-load-queue-has-nearly-quadrupled-in-a-single-year/) in its queue. By this June, that [figure reached 474 GW](https://www.utilitydive.com/news/texas-hits-pause-data-center-interconnections/827046/), more than five times record peak demand, about 90% of it data centers.\n\nThen Texas [hit pause](https://www.texastribune.org/2026/08/03/texas-data-center-project-audit-greg-abbott/). What began as [directions](https://gov.texas.gov/news/post/governor-abbott-directs-puc-and-ercot-to-shield-texans-from-data-center-infrastructure-costs) for data centers to pay for their own grid upgrades has since escalated to a [freeze](https://gov.texas.gov/news/post/governor-abbott-directs-tceq-to-halt-data-center-permits) on all new permits. If you care about AI and American reindustrialization, this is important to understand. Why did it do this?\n\n[![](https://d1lamhf6l6yk6d.cloudfront.net/uploads/2026/10/How-Texas-Hit-Pause-on-Data-Centers-scaled.png)](https://d1lamhf6l6yk6d.cloudfront.net/uploads/2026/10/How-Texas-Hit-Pause-on-Data-Centers-scaled.png)\n\nThe upcoming [election](https://www.texastribune.org/2026/09/21/texas-data-center-moratorium-water-energy/) is part of it, but the underlying issues are worth digging into. The first is the interconnection queue. This pause is just as much about how projects apply for approval as it is about the projects themselves. Developers routinely spam projects across several sites, and many are [speculative](https://www.bloomberg.com/news/articles/2026-08-12/most-electricity-sought-for-ai-data-centers-in-us-will-never-materialize) builds with no customer yet. Often these new developers have never even plugged in a GPU, let alone a power plant, so dealing with low-quality submissions puts ERCOT, which runs most of the state’s grid, in a [tough spot](https://www.texastribune.org/2026/06/17/texas-ercot-data-center-energy-grid/). Planners can’t tell which are real, and they don’t want ratepayers paying for upgrades built for projects that never show up.\n\n[![](https://d1lamhf6l6yk6d.cloudfront.net/uploads/2026/10/Little-of-Texass-Giant-Queue-has-Shown-Up-Yet-scaled.png)](https://d1lamhf6l6yk6d.cloudfront.net/uploads/2026/10/Little-of-Texass-Giant-Queue-has-Shown-Up-Yet-scaled.png)\n\nThe second issue is community alignment. Noise, water, emissions, and power bills are [top of mind](https://www.pewresearch.org/short-reads/2026/09/22/americans-views-of-data-centers-have-turned-more-negative/) for anyone who lives nearby. And regardless of the [reality](https://www.microsoft.com/en-us/microsoft-cloud/blog/2024/12/09/sustainable-by-design-next-generation-datacenters-consume-zero-water-for-cooling/) of these issues, people deserve [straight answers](https://www.texastribune.org/2026/09/14/texas-data-centers-abbott-water-survey-enforcement/) when a data center comes to town, and they [haven’t always gotten them](https://www.ksat.com/news/texas/2026/08/10/while-data-centers-boom-in-texas-their-plans-stay-shrouded-in-secrecy/) ([as of June, only 28 of 377 companies](https://www.texastribune.org/2026/08/03/texas-data-center-project-audit-greg-abbott/) had answered a state survey on their resource use). In Hood County, commissioners were asked to support a tax waiver for “Project Patriot” without knowing [who it was](https://www.texastribune.org/2026/06/02/texas-data-centers-hood-county-local-control-rural-water-power/). To be fair, code names are common while companies shop for sites since a famous buyer can drive up prices, but that logic becomes tougher to defend once officials vote on tax breaks.\n\nThe broader political backdrop is important, but I’ll be focusing on the [energy](https://a16z.com/decentralizing-the-electric-grid/) side: why it’s so hard to power a data center, all the ways developers are trying to do it anyway, and where things are likely headed.\n\n### What connecting to the grid actually means\n\nHow Amazon purchases power helps illustrate what’s changed. For the last decade, they’d find a utility with network capacity, sign up as a large load, then enter long-term contracts to [match](https://sustainability.aboutamazon.com/renewable-energy-methodology.pdf) their use on paper. These were often [purely financial](https://www.epa.gov/green-power-markets/financial-ppa), meaning you didn’t always have to prove the power could reach you, and the grid connection was easy because utilities had spare network capacity.\n\nThat’s no longer true. The grid is stretched thin, and almost any new large load or generator now requires an upgrade. [Power flows across every connected path](https://www.ferc.gov/sites/default/files/2020-05/ch1-3_0.pdf), so buying from one plant doesn’t reserve a route to your building (there are even markets for transmission congestion [rights](https://www.ercot.com/mktinfo/crr)).\n\n[![](https://d1lamhf6l6yk6d.cloudfront.net/uploads/2026/10/Every-plant-and-customer-shares-the-same-wires-scaled.png)](https://d1lamhf6l6yk6d.cloudfront.net/uploads/2026/10/Every-plant-and-customer-shares-the-same-wires-scaled.png)\n\nSo buyers went after firm power (available around the clock) they could claim more directly, typically by [restarting retired plants](https://www.constellationenergy.com/news/2024/Constellation-to-Launch-Crane-Clean-Energy-Center-Restoring-Jobs-and-Carbon-Free-Power-to-The-Grid.html) or by building next to existing ones. [Neither was a true escape](https://www.utilitydive.com/news/constellation-three-mile-island-crane-nuclear-ferc-waiver/821836/), and some of the loudest fights are over “colocation,” which [ERCOT describes](https://www.ercot.com/files/docs/2026/06/01/ERCOT-Trending-Topic-Grid-Reliability-Data-Centers-Net-Metering-Arrangements.pdf) as drawing power from a neighboring plant before it reaches the grid:\n\n- **Susquehanna:** Amazon [bought a campus](https://www.ans.org/news/article-5842/amazon-buys-nuclearpowered-data-center-from-talen/) next to Talen’s nuclear plant, but FERC, the federal grid regulator, [rejected Talen’s bid](https://www.utilitydive.com/news/ferc-interconnection-isa-talen-amazon-data-center-susquehanna-exelon/731841/) to send it more power directly. Utilities had argued it would let the campus dodge grid fees and push fixed transmission costs onto everyone else. After they [restructured the deal](https://www.sec.gov/Archives/edgar/data/1622536/000162253626000066/tln-20260630.htm), Amazon [pays for delivery like any other customer](https://www.powermag.com/talen-amazon-launch-18b-nuclear-ppa-a-grid-connected-ipp-model-for-the-data-center-era/).\n- **Freestone:** CyrusOne’s 760 MW campus beside Constellation’s gas plant needed [approval from the Public Utility Commission of Texas (PUCT)](https://tcss.legis.texas.gov/resources/UT/htm/UT.39.htm#39.169), since it effectively takes much of the plant’s output from everyone else. The PUCT [said yes](https://www.constellationenergy.com/news/2026/05/constellation-reports-first-quarter-2026-results.html) in May, as long as the campus can [cut its use](https://www.ercot.com/files/docs/2026/06/01/ERCOT-Trending-Topic-Grid-Reliability-Data-Centers-Net-Metering-Arrangements.pdf) or switch to backup power within 30 minutes of an ERCOT call.\n- **Armstrong County:** Two Crusoe data centers beside a wind farm got [the same rule](https://www.ercot.com/files/docs/2026/06/01/ERCOT-Trending-Topic-Grid-Reliability-Data-Centers-Net-Metering-Arrangements.pdf), and [the second, approved in July](https://www.utilitydive.com/news/texas-approves-ai-data-center-co-location-next-to-wind-farm-with-curtailme/826617/), must also shed its entire load, so together they’d cut nearly twice what the wind farm can produce.\n\nInterconnection studies are how grid planners identify the wires and substations that need upgrades for any addition to the network. ERCOT used to review studies individually under rules [built for 40 to 50 large loads at a time](https://www.utilitydive.com/news/ercots-large-load-queue-jumped-almost-300-last-year-official/808820/), but 2025 brought 225 new requests by mid-November. So this June, the PUCT [approved a new batch approach](https://www.ercot.com/news/release/06182026-puct-approves-ercots). Under “Batch Zero,” ERCOT studies large loads of 75 MW or more together and allocates grid capacity among them.\n\nPrimarily, the studies ask what happens when something breaks. [NERC’s standard](https://www.nerc.com/pa/Stand/Reliability%20Standards/TPL-001-5.1.pdf), the baseline for reliability across North America, covers a broad set of outage scenarios, with [ERCOT adding its own requirements](https://www.ercot.com/files/docs/2026/05/29/June-1-2026-Plannng-Guide.pdf). Planners might simulate a transformer outage, then knock out a line or generator on top of that. Maintaining that reliability standard without shedding more load often means building additional infrastructure.\n\n[![](https://d1lamhf6l6yk6d.cloudfront.net/uploads/2026/10/Two-lines-can-serve-an-area-comfortably-until-one-trips-scaled.png)](https://d1lamhf6l6yk6d.cloudfront.net/uploads/2026/10/Two-lines-can-serve-an-area-comfortably-until-one-trips-scaled.png)\n\nA newer risk is load dropping off the grid all at once. Many data centers switch to backup power at the first voltage dip to protect their hardware, so one bad fault can [pull an enormous load](https://www.jdsupra.com/legalnews/nerc-computational-load-updates-6702832/) off the grid in seconds. This [happened](https://insidelines.pjm.com/pjm-dominion-review-large-load-transfer-event/) earlier this year in Virginia, but was fortunately handled well.\n\nTexas has even less room for error since ERCOT’s grid is largely [isolated](https://www.ercot.com/files/docs/2025/05/12/ERCOT-Grid-Insights-Electricity-Connection-and-Transfer.pdf). Under some conditions, ERCOT can lose only [about 3.2 GW](https://www.ercot.com/files/docs/2026/09/16/QSA-Results-and-Large-Load-IROL-Mitigation-Plans_final.pdf) of load at once before causing issues. A new voltage [ride-through rule](https://www.ercot.com/mktrules/issues/NOGRR282) now requires new data centers to stay connected through routine faults, and I’ve even heard of labs running dummy jobs after a training run fails just to keep load from dropping abruptly.\n\n[![](https://d1lamhf6l6yk6d.cloudfront.net/uploads/2026/10/One-Virginia-line-failure-dropped-more-load-than-Texas-can-lose-at-once-scaled.png)](https://d1lamhf6l6yk6d.cloudfront.net/uploads/2026/10/One-Virginia-line-failure-dropped-more-load-than-Texas-can-lose-at-once-scaled.png)\n\nAll of this can sound overly conservative, but the system was designed to put reliability ahead of cost. Put simply, the grid is built for the hot summer days and frigid winters when failure can mean life or death. That duty is what makes sizing the grid so hard; you build for a few peak hours but pay for it all year.\n\n[![](https://d1lamhf6l6yk6d.cloudfront.net/uploads/2026/10/The-grid-is-built-for-a-peak-it-neared-for-only-about-200-hours-scaled.png)](https://d1lamhf6l6yk6d.cloudfront.net/uploads/2026/10/The-grid-is-built-for-a-peak-it-neared-for-only-about-200-hours-scaled.png)\n\nSo who does pay for all this resilience? Texas typically splits transmission costs by each large customer’s demand during the grid’s summer peaks, so a big load that ramps down on the hottest afternoons can skip much of its share of the transmission bill. In July, regulators [proposed](https://interchange.puc.texas.gov/Documents/58000_8_1664102.PDF) counting all 12 monthly peaks instead and [charging](https://www.sos.texas.gov/texreg/archive/July242026/Proposed%20Rules/16.ECONOMIC%20REGULATION.html) large loads as if they ran at full size. In other words, large buyers would pay in proportion to how big their electricity pipes need to be, not how much is flowing through them.\n\nSounds simple enough, but splitting up costs is often the slowest part of interconnection. An upgrade built for one campus may also improve reliability for existing customers or make room for future growth that’s hard to value up front. And if any new development runs over budget or its load never shows up, everyone else is forced to cover whatever the developer’s commitments didn’t.\n\nAnd those commitments are surprisingly cheap to make. The PUCT’s [new large-load rules](https://interchange.puc.texas.gov/Documents/58481_218_1684654.PDF), effective October 8, charge a flat $100,000 study fee plus a $50,000-per-MW deposit. The deposit weeds out some speculative projects, but it’s a thin filter. ERCOT can reassign a project’s capacity if it falls two years behind, but even a project that loses its capacity forfeits just 20% of the deposit (at least $10 million on a 1 GW campus), plus whatever the utility has already spent. Most importantly, the deposit typically only backs the upgrades built for that project, not the more expensive regional lines whose cost everyone on the grid shares.\n\nFully connecting a large data center can take [5 to 10 years](https://arxiv.org/abs/2509.07218). To accelerate deployment, a [phased connection approach](https://www.crusoe.ai/resources/newsroom/crusoe-expands-ai-data-center-campus-in-abilene-to-1-2-gigawatts) is becoming [more common](https://www.sdxcentral.com/news/xai-colossus-memphis-power-tva/), which gives the utility more gradual targets to plan around, as well as a way for the developer to prove they can handle everything they’ve asked for. All of this also assumes Batch Zero is moving, which it isn’t right now. ERCOT has even [paused approvals](https://www.ercot.com/files/docs/2026/08/20/Batch-Zero-Verification-and-Audit-PUCT-Presentation.pdf) for data centers of 75 MW or more to switch on, including 17 that had finished every other ERCOT step. Until the audit’s December report settles which projects are eligible, ERCOT can’t study them together, so the timeline is [“TBD”](https://www.ercot.com/files/docs/2026/09/11/14-Batch-Zero-Update.pdf) and [the load forecast is on hold](https://www.ercot.com/files/docs/2026/08/20/Batch-Zero-Verification-and-Audit-PUCT-Presentation.pdf).\n\n### What bringing your own power solves\n\nFor a developer facing the interconnection queue, skipping the grid entirely looks appealing. Idle GPUs [cost](https://epoch.ai/data-insights/ai-datacenter-cost-breakdown) far more than the electricity to run them, so speed matters most — what folks call “time to power.” That’s why developers are planning to bring their own power on site (“behind the meter”), but almost always alongside a connection to the grid, or as a bridge to one:\n\n- **Abilene:** The Oracle campus [runs on grid power with gas backup](https://www.crusoe.ai/resources/blog/an-inside-look-at-the-abilene-ai-data-center). Next door, Crusoe announced a 900 MW Microsoft campus with its own [on-site plant](https://www.crusoe.ai/resources/newsroom/crusoe-announces-new-900-mw-ai-factory-campus-in-abilene-texas-to-support-microsoft-ai-infrastructure), but the CEO of Lancium, Crusoe’s partner on the site, has [described gas generation as backup](https://westtexastribune.org/2026/05/05/lancium-ceo-addresses-abilenes-concerns/).\n- **Shackelford County:** Vantage is building a campus with 1.4 GW of compute for Oracle and OpenAI, designed to run off-grid on [on-site gas](https://epoch.ai/publications/openai-stargate-where-the-us-sites-stand). But [its site plan](https://records.tceq.texas.gov/cs/idcplg?IdcService=TCEQ_EXTERNAL_SEARCH_GET_FILE&dID=8984027&Rendition=Web) includes a switchyard beside a high-voltage line — curious!\n- **Pecos County:** Pacifico describes its planned microgrid (a behind-the-meter setup) at GW Ranch as [never drawing from ERCOT](https://www.pacificoenergy.com/gw-ranch), yet the site’s new owner, Amazon, says it’s [designed to join the grid](https://www.aboutamazon.com/news/company-news/amazon-pecos-county-texas-data-center-clean-energy-jobs) once it can connect.\n- **West Texas:** Under a [20-year agreement](https://www.chevron.com/newsroom/2026/q2/chevron-signs-20-year-power-agreement-with-microsoft-for-west-texas-data-center), Chevron plans to build a dedicated gas plant beside a planned Microsoft campus that won’t initially touch the ERCOT grid, though Chevron has applied for a connection. Chevron now says the permit freeze [could push its final investment decision into 2027](https://www.semafor.com/article/10/01/2026/texas-politics-could-delay-investment-decision-for-huge-chevron-data-center), but it still expects first power by 2028.\n- **Armstrong County:** The Google campus Crusoe is building beside a wind farm is [tied to both the farm and the grid from day one](https://www.crusoe.ai/resources/newsroom/crusoe-developing-data-center-campus-in-armstrong-county-texas), with Crusoe calling it “[across the meter](https://www.crusoe.ai/resources/blog/co-located-power-for-ai-data-centers),” which I’ll admit is catchy.\n\nSemiAnalysis is already tracking [75 GW of equipment orders](https://newsletter.semianalysis.com/p/everyone-says-datacenter-moratoriums) for behind-the-meter assets, but every site I’m aware of intends to connect to the grid as soon as it can, chiefly because on-site power almost always costs more. So, once the grid is available, say in year five, you switch.\n\n[![](https://d1lamhf6l6yk6d.cloudfront.net/uploads/2026/10/Five-ways-a-campus-can-pair-its-own-power-with-the-grid-1-scaled.png)](https://d1lamhf6l6yk6d.cloudfront.net/uploads/2026/10/Five-ways-a-campus-can-pair-its-own-power-with-the-grid-1-scaled.png)\n\nIn the meantime, pairing on-site assets with even a partial connection is smart for the same reasons we built a grid in the first place. When one plant trips, the rest of ERCOT’s [1,460-plus generating units](https://www.ercot.com/files/docs/2022/02/08/ERCOT_Fact_Sheet.pdf) cover for it, but an islanded load (cut off from the grid) doesn’t have that luxury. The grid also provides things we take for granted, like [inertia](https://www.osti.gov/biblio/1659820), [fault current](https://www.osti.gov/biblio/1870461), steady voltage, and [black start](https://www.ercot.com/files/docs/2025/06/20/ERCOT-Grid-Insights-Black-Start.pdf). An island has to supply all of that itself — power systems folks know how hard this can be.\n\n[![](https://d1lamhf6l6yk6d.cloudfront.net/uploads/2026/10/An-island-has-to-build-what-the-grid-provides-scaled.png)](https://d1lamhf6l6yk6d.cloudfront.net/uploads/2026/10/An-island-has-to-build-what-the-grid-provides-scaled.png)\n\nAI workloads make the job even harder. At xAI’s first Memphis site, swings of 10 to 20 MW several times a second were [wearing out turbine shafts](https://newsletter.semianalysis.com/p/what-is-so-hard-about-behind-the) until xAI added 150 MW of Tesla Megapacks. A grid ERCOT’s size dilutes swings like that, but on a private plant the turbines really feel it. Expect more batteries and other energy storage as rack-level power density grows and swings become more dramatic.\n\nThen there’s fueling a site. [Winter Storm Uri’s](https://www.ercot.com/files/docs/2021/02/24/2.2_REVISED_ERCOT_Presentation.pdf) lesson is that gas plants can [fail together](https://www.nerc.com/globalassets/standards/projects/2021-07/ferc-presentation-phase-2.pdf). And since they tend to keep little fuel on site (NERC calls gas a [“just-in-time” fuel](https://www.nerc.com/globalassets/who-we-are/news/2025/10/2025-october-reliability-insights_final.pdf)), spare turbines don’t always help. [Sometimes the pipeline doesn’t even exist yet](https://sourcenm.com/2026/08/17/proposed-gas-pipeline-for-project-jupiter-data-center-delayed-to-2027-filings-show/). Solar trades that fuel risk for the sun and weather, and at gigawatt scale, you need a lot of batteries. Keeping a 1 GW campus running through one 14-hour winter night takes 14 GWh from batteries, [about half of all the battery storage on ERCOT’s grid](https://modoenergy.com/research/en/ercot-bess-buildout-16-gw-q2-2026-growth-slowing) as of June. For an island seeking 100% uptime, covering rare events like a cloudy week or another Uri gets expensive.\n\nWhatever the fuel, you want an island that fails gracefully and predictably, with no single point of failure. Even nuclear, about as reliable as power plants get, runs only about [92% of the time](https://www.eia.gov/todayinenergy/detail.php?id=65904), mostly because each reactor goes offline for weeks to refuel. Redundancy in this case means effectively an entire second power plant. Thus, behind-the-meter setups favor modularity, like the [more than 500 gas engines](https://newsletter.semianalysis.com/p/what-is-so-hard-about-behind-the) of about 4 MW each planned for Shackelford, though hundreds of engines can be a pain to maintain.\n\nFull reliability for an island is very, very hard, but some labs and hyperscalers have shown that, forced to choose between reliability and speed, they’ll pick speed. Meta has turned to tents with [no backup generators](https://newsletter.semianalysis.com/p/meta-superintelligence-leadership-compute-talent-and-data), and SemiAnalysis finds buyers [growing more willing to accept outages](https://newsletter.semianalysis.com/p/what-is-so-hard-about-behind-the), with some island designs aiming for as little as 99% uptime, or about 88 hours of downtime a year. With [GPU time this expensive](https://newsletter.semianalysis.com/p/the-great-gpu-shortage-rental-capacity), that still beats years of waiting, so for many buyers a temporary island makes sense even if it’s messy.\n\nA “private grid” that ties several plants and campuses together can take back many of the benefits a lone island gives up, at least in theory. But today Texas, like most states, only allows building your own power within tight limits:\n\n- **Supplying yourself:** You [aren’t a utility](https://tcss.legis.texas.gov/resources/UT/htm/UT.31.htm) if you supply only yourself, your employees, or your tenants, and nobody resells the power.\n- **Running a private use network:** You can also run on co-located generation, [sell the surplus into the grid](https://www.jdsupra.com/legalnews/private-use-networks-self-generation-4515203/), and draw from it when you fall short. This is the model for the Armstrong County campus, and for the West Texas one once it connects.\n  - **Selling to a neighbor:** If you sell to the factory across the road, you need a [retail electric provider certificate](https://www.puc.texas.gov/agency/rulesnlaws/subrules/electric/25.107/25.107.pdf).\n  - **Stringing a wire:** Build your own line, and you’re probably running into the local utility’s [service territory](https://www.puc.texas.gov/agency/rulesnlaws/subrules/electric/25.101/25.101.pdf).\n\nThe Cato Institute’s [consumer-regulated electricity](https://www.cato.org/briefing-paper/case-consumer-regulated-electricity-private-electricity-grids-offer-parallel-path) proposal would loosen those limits by allowing private utilities to serve multiple customers across their own network. This isn’t an entirely new idea; Utah’s [SB 132](https://le.utah.gov/Session/2025/bills/enrolled/SB0132.pdf) lets loads of 100 MW or more contract for a fully off-grid system. Texas currently doesn’t let a network like this serve multiple customers, but if the demand for power remains insatiable, I’d expect the more permissive states to win larger chunks of the buildout with this “Wild West” utility structure. (However, you may also risk a utility “[death spiral](https://www.utilitydive.com/news/as-data-centers-go-off-grid-utilities-face-new-cost-and-planning-risks/811944/),” with the grid’s fixed costs falling on fewer and fewer customers.)\n\nThe flip side is a utility building the island itself. Outside ERCOT, El Paso Electric plans to put [813 small gas generators from ERock](https://interchange.puc.texas.gov/Documents/59076_1_1564187.PDF) (366 MW in all) beside Meta’s new campus and run them as an island, on Meta’s dime, for up to five years. This is an option because, unlike the transmission and distribution utilities inside ERCOT, it still owns power plants. After the island period, it would connect the plant to its grid and could seek to spread the cost across all its customers, though in September administrative judges [recommended](https://interchange.puc.texas.gov/Documents/59076_176_1686197.PDF) approval only if those customers are protected.\n\nAnything that runs on fuel also needs an air permit that matches how it operates, so a diesel generator permitted only for emergencies can’t run all the time. Optimistically, permits can [come fast](https://newsletter.semianalysis.com/p/what-is-so-hard-about-behind-the) when things work. Sometimes they [don’t](https://news.constructconnect.com/oracle-drops-gas-turbine-plan-for-its-massive-project-jupiter-turns-to-bloom-fuel-cells), though. In Texas, the freeze now blocks them for data centers until the audit is done.\n\nWe should also ask what instances of “bridge” gas are actually bridging to. xAI’s first two Memphis data centers answer that in different ways. The first ran temporary turbines off [an existing gas main](https://www.mlgw.com/images/content/files/pdf/new/xAI%202025%20Update.pdf) until the grid arrived, then [began removing them](https://memphischamber.com/blog/press-release/xai-phase-one-substation-63-providing-150mw-of-power-to-facility/). Along the way, it [ran dozens without air permits](https://www.selc.org/news/inside-memphis-fight-against-xai/). For the second, xAI built its plant [across the state line](https://www.wsmv.com/2026/04/14/naacp-sues-xai-alleging-unlawful-operation-gas-turbines-southaven/) in Southaven, Mississippi, but a July order [requires all 69 turbines to retire](https://tippahnews.com/mississippi-news/mississippi-sets-retirement-schedule-for-xai-turbines-allows-some-to-run-past-deadline/) by mid-2027 as a permanent 1.2 GW plant goes up in their place. One bridge led to the grid, and the other to a power plant of xAI’s own.\n\nIn August, though, the federal Tennessee Valley Authority (TVA) [agreed](https://www.aol.com/articles/tva-board-approves-agreement-spacexai-234602000.html) to serve that data center directly, too. Turns out it’s hard to stay away from the grid!\n\n### What flexibility can buy\n\nA campus that can keep itself running can also be easier for the grid to accommodate, even welcome. It’s a large paying customer whose demand can “flex” when power is tight, whether by cutting its draw or exporting surplus power. This is how xAI got approved for grid power at its second Memphis site. What made its promise to flex credible was its ability to carry its entire load for four hours on its own power, and what the CEO of Memphis Light, Gas and Water called [“the world’s largest grid-connected battery system.”](https://www.canarymedia.com/articles/batteries/xai-massive-battery-memphis-data-center)\n\nBatteries are only one way to flex. A campus can also [shift computing](https://cloud.google.com/blog/products/infrastructure/using-demand-response-to-reduce-data-center-power-consumption) to other hours or data centers, or switch to its own generators. So how much room could flexibility open up? [Tyler Norris and colleagues at Duke](https://nicholasinstitute.duke.edu/publications/rethinking-load-growth) estimated that, setting transmission limits aside, ERCOT could add about 10 GW of new load without new generation if that load gave up 0.5% of its yearly grid electricity. Since the average cutback lasts about two hours, it’s also conveniently battery-shaped. Building on this, a [study of PJM (the largest US power market) by Camus, encoord, and Princeton](https://www.camus.energy/flexible-data-center-report) found that for each GW of new data center load, making 20% of that load flexible would save other customers $78 million a year, while bringing its own capacity for the other 80% would keep another $326 million off their bills.\n\n[![](https://d1lamhf6l6yk6d.cloudfront.net/uploads/2026/10/Flexible-campuses-could-add-about-100-GW-without-new-power-plants-1-scaled.png)](https://d1lamhf6l6yk6d.cloudfront.net/uploads/2026/10/Flexible-campuses-could-add-about-100-GW-without-new-power-plants-1-scaled.png)\n\nFor flexibility to be valuable, it’s important that it’s always available when operators need it. In Texas, generators already work this way under [connect-and-manage](https://www.utilitydive.com/news/connect-and-manage-grid-interconnection-ferc-ercot-transmission-planning/698949/). Put simply, they can hook up early as long as ERCOT can cut them down when lines are congested. Generators can live with that because at worst they sell less for a while, but a data center that has promised its customers uptime is more challenging. Some loads, like [Bitcoin miners](https://www.cnbc.com/2023/09/06/texas-paid-bitcoin-miner-riot-31point7-million-to-shut-down-in-august.html), have made the trade anyway. [Batch Zero](https://www.ercot.com/files/docs/2026/06/18/ERCOT-Trending-Topic-New-Batch-Connection-Process-for-Large-Electricity-Users.pdf) gives large loads two optional paths here:\n\n- **Bring your own power:** A campus can count its own power plant toward its size as long as it can cut back within [one minute](https://www.willkie.com/publications/2026/06/ercot-approves-implementing-new-batch-zero-process-for-large-load-interconnections) if the plant fails. So far, 11 Batch Zero projects have picked this path.\n- **Agree to cuts:** A campus can draw up to the full amount it asked for, but ERCOT can automatically cut anything above its guaranteed share whenever lines are full.\n\n[![](https://d1lamhf6l6yk6d.cloudfront.net/uploads/2026/10/Two-ways-to-connect-more-than-the-grid-%E2%80%A8can-guarantee-scaled.png)](https://d1lamhf6l6yk6d.cloudfront.net/uploads/2026/10/Two-ways-to-connect-more-than-the-grid-%E2%80%A8can-guarantee-scaled.png)\n\nA campus could also pay its neighbors to cut their load instead. In PJM, [Google is funding Voltus](https://www.utilitydive.com/news/google-virtual-power-plant-vpp-pjm-voltus/821838/) to pool up to 100 MW of batteries, thermostats, and other flexible devices across a territory. But PJM only counts what it trusts the pool to deliver, and it’s a [capacity deal](https://www.latitudemedia.com/news/google-is-voltus-first-bring-your-own-capacity-customer/) that helps the whole grid at its peak, not a fix for any one congested line. That’s a harder sell in Texas, an energy-only market where transmission is the main bottleneck. Texas has also [barred](https://interchange.puc.texas.gov/Documents/58881_105_1628395.PDF) colocated campuses from getting paid for [similar services](https://interchange.puc.texas.gov/Documents/59220_69_1668205.PDF), since under [SB 6](https://www.utilitydive.com/news/texas-law-gives-grid-operator-power-to-disconnect-data-centers-during-crisi/751587/) they already have to shut off when ERCOT tells them.\n\nEven so, Texas has been a leader in distributed resources. One [Base Power fleet, run with the co-op GVEC](https://www.gvec.org/gvec-and-base-power-partnership/), passed ERCOT’s pilot tests to sell directly into the wholesale market on its first attempt, and is now expanding to 50 MW. These pilots are important; planners need that kind of proof before they’ll design around these fleets. But once trusted, distributed resources can rapidly add capacity without waiting for an expensive new “[peaker](https://en.wikipedia.org/wiki/Peaking_power_plant)” power plant, lines, substations, or a lengthy interconnection process.\n\nOther hardware can help, too. Unlike legacy steel units, a solid-state transformer uses semiconductor switches, so software can measure and steer the power flowing through it. Alongside network upgrades like reconductoring (restringing lines with higher-capacity wire) and dynamic line ratings (rating lines for actual weather instead of worst-case conditions), that greater visibility and control can squeeze more out of wires ratepayers already funded. It’s a big reason we backed [Heron Power](https://a16z.com/announcement/investing-in-heron-power/), which is set to install its solid-state transformers at a [West Texas battery site with RWE](https://www.globenewswire.com/news-release/2026/09/21/3365509/0/en/heron-power-and-rwe-sign-pilot-agreement-outline-path-to-multi-year-capacity-reservation.html).\n\nThe problem is that most of these tools help operators keep things running day to day, but planners don’t always count them when they size upgrades. Nothing in physics forces that, though. A September [study by Piq Energy](https://www.piqenergy.com/research/piq-energy-base-power---flexibility-without-curtailment.pdf), using [Base Power](https://a16z.com/announcement/investing-in-base-power/)’s data on potential fleets, found that about 80 MW of home batteries, strategically sited to relieve transmission constraints, could resolve all overloads triggered by a hypothetical new 100 MW data center near Fort Worth.\n\nBatch Zero doesn’t consider things like this yet. It [still plans upgrades for a flexible campus’s full planned load](https://epeconsulting.com/epe-intelligence/news/new-pathway-and-deadlines-in-ercot-s-large-load-batch-zero-provisional-controllable-load-resource-pclr), since that path is a bridge to firm service, and there’s no option to stay flexible for good in exchange for smaller upgrades. Flexibility gets a campus connected sooner, but it doesn’t shrink the upgrades. Planners could instead size them smaller by crediting flexibility and other resources that relieve the same bottleneck, assuming they’re measured in real time and perform reliably.\n\nAll of this saves time and money by getting more out of what’s already in the ground, but no amount of flexibility gets the grid out of building more generation and wires for all the demand coming down the pipe.\n\n### Getting to hundreds of gigawatts\n\nOn-site power and flexibility will decide how the next few campuses energize, but the labs and hyperscalers I talk to worry most about scale. Their power teams tend to split in two: one picks sites and equipment for the next couple of years, and the other asks how to connect hundreds more gigawatts after 2030.\n\nThis is a lot! Run, say, 100 GW all year and it’s 876 TWh, [about a fifth](https://www.eia.gov/energyexplained/electricity/use-of-electricity.php) of what the country used in 2025. Here’s what power developers [told the Energy Information Administration](https://www.eia.gov/todayinenergy/detail.php?id=67205) (EIA) they planned to add in 2026 across the entire grid.\n\n[![](https://d1lamhf6l6yk6d.cloudfront.net/uploads/2026/10/Most-new-grid-capacity-planned-for-2026-is-solar-and-batteries-scaled.png)](https://d1lamhf6l6yk6d.cloudfront.net/uploads/2026/10/Most-new-grid-capacity-planned-for-2026-is-solar-and-batteries-scaled.png)\n\nEvery source helps, and much of it is headed to Texas anyway. But at last year’s average capacity factors (how much plants actually produce versus their maximum), the planned [solar, wind](https://www.eia.gov/electricity/monthly/epm_table_grapher.php?t=epmt_6_07_b), and [gas plants](https://www.eia.gov/electricity/monthly/epm_table_grapher.php?t=epmt_6_07_a) would make around 150 TWh a year, or about a sixth of that 876 TWh.\n\nTo be fair, that gas bar likely understates [what’s being built](https://www.distilled.earth/p/eight-new-gas-plants-will-power-amazons), since [EIA’s survey only counts plants tied to the grid](https://www.eia.gov/survey/form/eia_860/instructions.pdf). In this way, much of the 75 GW of on-site power equipment already on order could be ghost capacity that charts like this one will miss. Still, gas remains popular because it generally runs whenever you need it. And because of that, the constraint is mostly [getting the equipment](https://www.sec.gov/Archives/edgar/data/0001996810/000199681026000147/gevpressrelease2q26.htm) in the first place, so buyers are turning to alternatives that can be [easier to find](https://www.latitudemedia.com/news/is-the-gas-turbine-bottleneck-solving-itself/), like [reciprocating engines](https://www.powermag.com/data-centers-are-turning-to-gas-generators-for-prime-power-to-eliminate-long-lead-times-for-grid-connections/) and [fuel cells](https://investor.bloomenergy.com/press-releases/press-release-details/2026/Bloom-Energy-and-Oracle-Expand-Strategic-Partnership-to-Deploy-up-to-2-8-GW-to-Accelerate-AI-Infrastructure-Build-Out/default.aspx).\n\nThat said, gas feels like an incomplete answer to me. I’m no Greenpeace warrior, but running 100 GW around the clock at gas plants’ [average rate](https://www.eia.gov/tools/faqs/faq.php?id=74&t=11) would release nearly 8% of the country’s [energy-related emissions](https://www.eia.gov/environment/emissions/carbon/). Often the easiest equipment to get is even [less efficient](https://www.eia.gov/electricity/annual/html/epa_08_02.html), too.\n\n[![](https://d1lamhf6l6yk6d.cloudfront.net/uploads/2026/10/Running-100-GW-on-gas-would-burn-more-Gas-than-the-US-exported-as-LNG-in-2025-scaled.png)](https://d1lamhf6l6yk6d.cloudfront.net/uploads/2026/10/Running-100-GW-on-gas-would-burn-more-Gas-than-the-US-exported-as-LNG-in-2025-scaled.png)\n\nSolar is compelling because it already has the production scale the labs are aiming for. The problem is that it’s mostly in China. The world [added more than 600 GW](https://www.solarpowereurope.org/press-releases/new-report-global-solar-market-hits-new-record-of-664-gw-installation-in-2025-as-global-solar-fleet-passes-3-tw) in 2025, but China alone makes [more than 80% of the world’s solar components](https://www.iea.org/reports/solar-pv-global-supply-chains/executive-summary) and [battery cells](https://www.iea.org/reports/global-ev-outlook-2026/manufacturing-and-trade). From what I can tell, Chinese suppliers don’t mind selling to us that much, at least partly because they see our scale-up as “cute.” However, China [reportedly weighed](https://finance.yahoo.com/sectors/energy/articles/exclusive-china-weighs-curbs-exports-074947904.html) curbing exports of specific solar manufacturing equipment. Washington has also put on pressure, with [forced-labor shipment holds](https://pv-magazine-usa.com/2022/11/11/due-to-forced-labor-concerns-u-s-ports-have-blocked-over-1000-shipments-of-solar-components/), [new tariffs](https://pv-magazine-usa.com/2026/08/07/us-announces-tariffs-minimum-import-price-on-polysilicon-imports/), and [phasing out wind and solar credits](https://www.irs.gov/pub/irs-drop/n-25-42.pdf). Despite this, Elon is aiming [for 200 GW a year](https://pv-magazine-usa.com/2026/01/26/elon-musk-at-wef-spacex-and-tesla-to-produce-100-gw-each-of-pv-per-year-in-the-u-s-this-decade/) of US solar manufacturing on his own, [obviously](https://x.com/elonmusk/status/1925872357781983522?s=20) solar-pilled.\n\nScaling firm power that isn’t gas is much more complicated. [Uprates](https://www.prnewswire.com/news-releases/georgia-power-agreement-with-google-to-provide-approximately-900-million-in-projected-benefits-for-customers-and-advance-nuclear-energy-in-georgia-302885197.html) and restarts can [squeeze](https://www.reuters.com/business/energy/google-enters-massive-36-gw-power-deal-with-constellation-energy-2026-10-06/) a little more from the existing nuclear fleet, but the real upside is new reactors, as [we’ve argued before](https://a16z.com/how-to-scale-nuclear-power/). [Meta](https://about.fb.com/news/2026/01/meta-nuclear-energy-projects-power-american-ai-leadership/) and [Amazon](https://www.aboutamazon.com/news/sustainability/amazon-smr-nuclear-energy) have signed big deals, but much of it is still options and targets. So far, the military has been a stronger [buyer](https://breakingdefense.com/2026/08/army-taps-5-vendors-to-build-nuclear-microreactors-with-2-2b-pot/) to build microreactors on its bases, which is how factory-built reactors can learn to get faster and cheaper (blame EPC as much as the NRC). Geothermal could also leverage drilling (something Texas knows well) for repeatable power — [Google](https://fervoenergy.com/fervo-energy-and-google-sign-396-mw-ppa/) and [Meta](https://www.businesswire.com/news/home/20240826755596/en/Sage-Geosystems-and-Meta-Announce-Agreement-for-Next-Generation-Geothermal-Power-Generation) appear quite interested.\n\nRegardless of the power source, it all still ends up waiting on other equipment like transformers and switchgear, and all the crews to install them. Large power transformers now take [more than two years](https://www.powermag.com/transformers-in-2026-shortage-scramble-or-self-inflicted-crisis/) to arrive, and the FCC has [limited new foreign-made inverters](https://docs.fcc.gov/public/attachments/DA-26-786A1.pdf) alongside an [August emergency order](https://www.whitehouse.gov/presidential-actions/2026/08/declaring-a-national-emergency-to-secure-the-united-states-bulk-power-system/) that could further bar Chinese-made equipment from the grid.\n\nSomeone also has to build the wires. In 2008, Texas regulators ordered the [CREZ lines](https://www.bakerinstitute.org/sites/default/files/2020-11/import/ces-pub-texascrez-111720.pdf) to carry West Texas wind, then spread their $7 billion cost across every ratepayer. Now they’re approving even bigger [765 kV lines](https://www.texastribune.org/2026/08/28/transmission-lines-texas-energy/), but it’s going [slower](https://thetexan.news/issues/energy/here-s-the-current-state-of-the-plan-to-build-765-kv-transmission-lines-across/article_b7e8c5bb-35c7-42d7-bed9-04f243de1927.html) than many would like. Some of that is just (unfortunately) typical construction, which is slow and expensive anywhere, but there’s also a myriad of additional regulatory hurdles on top. The [federal permitting deal taking shape in Washington](https://www.energy.senate.gov/press/rep/lee-capito-heinrich-and-whitehouse-introduce-bipartisan-american-affordability-and-jobs-act-of-2026/) could help move things along if Congress can pass it.\n\nAdmittedly, I’m more confident that we’ll need a lot of power than I am about the exact shape it takes. My bet is that a handful of setups, depending on geography and flexibility, get built over and over. Maybe on-site gas and batteries carry a campus until its grid connection shows up, then stick around as backup to flex when the grid is tight. Solar gets layered on now where it fits, and geothermal and reactors come in once they prove out.\n\nPast 2030, it’s even harder to say who ends up building and owning all that power. One answer is that the same company builds both the plant and the campus (vertical integration), which Google’s [purchase of Intersect](https://abc.xyz/investor/news/news-details/2025/Alphabet-Announces-Agreement-to-Acquire-Intersect-to-Advance-U-S--Energy-Innovation-2025-DVIuVDM9wW/default.aspx) may signal. Another is that oil and gas companies, like Chevron or Williams, become [broader grid builders](https://travisfisher.substack.com/p/socrates-south-shows-the-benefits), and it isn’t hard to picture them, or “neo-utilities” like NRG and NextEra, building private grids that serve several campuses, assuming the law enables it.\n\nI don’t know which way it goes yet, but they’ll all be buying from the same equipment makers. That market is huge and surprisingly ill-equipped to meet inflecting demand. Given that, I see two major ways for startups to break in:\n\n- **Integration:** Some take familiar hardware and win on integration or business model, the way Base Power runs home batteries as a trusted aggregated resource.\n- **Technology:** Others bring new technology so much better that early adopters will take a chance on it, which is what Heron Power is aiming to do with solid-state transformers.\n\nA third pitch, crudely put as “worse but faster,” sells well in a shortage, but I’d ask what those profits are being reinvested in, because it might get hard to compete if broader supply catches up.\n\nIndeed, shortages like these are an opening for startups, but it helps to understand why incumbents aren’t quick to fill them. The last bet on a turbine boom ended in a $22 billion GE Power write-down and [helped cost GE’s CEO his job](https://www.bostonglobe.com/business/2018/10/01/john-flannery-out-general-electric-ceo/7QRPwEHxACP1PON92Vq8WJ/story.html). A startup has to survive the busts incumbents are planning around, as well as compete globally with Siemens Energy, Mitsubishi Power, and all sorts of suppliers in places like India and China. Customers may pay for speed today, but keeping them will take reliable, competitively priced equipment and a service team that knows what it’s doing.\n\nEvery step of site development is hard. Vendors like GE Vernova now take [nonrefundable deposits](https://www.gevernova.com/sites/default/files/gev_webcast_transcript_10222025.pdf) just to reserve a manufacturing slot, leaving developers with a [chicken-and-egg problem](https://newsletter.semianalysis.com/p/what-is-so-hard-about-behind-the). Lenders want a long-term contract with a solid customer, who wants a credible timeline, and that timeline takes deposits the developer usually needs lenders to fund. Bring in an unproven vendor and the loop gets even harder to close (and markets notice fast when it [breaks](https://amarillotribune.org/2025/12/12/fermi-stock-drops-after-termination-of-150-million-construction-agreement/)). Once it closes, everything else still [has to go right](https://www.bloomberg.com/news/articles/2026-09-24/oracle-cites-force-majeure-to-shield-itself-on-controversial-data-center).\n\nFor a new vendor, even getting into a campus’s first phase is difficult. Hardly anyone has placed a large, firm order for data center power equipment without thousands of hours of operation. For example, [FTAI’s big order](https://www.globenewswire.com/news-release/2026/07/22/3331360/35538/en/ftai-announces-1-465-billion-gas-turbine-generator-set-order-through-j-f-power-systems.html) rests on the CFM56, a jet engine that has logged [more than a billion flight hours](https://www.safran-group.com/pressroom/cfm56-engine-fleet-surpasses-one-billion-engine-flight-hours-2019-06-04), while Crusoe [stepped back from Boom](https://techcrunch.com/2026/09/25/crusoe-abandons-1-25b-plan-to-use-boom-turbines-at-ai-data-centers/) as Boom’s first engine core was still [gearing up for tests](https://aviationweek.com/business-aviation/aircraft-propulsion/boom-supersonic-gears-engine-prototype-core-testing). So even credible teams building awesome technology face a cold-start problem. Thus, getting your product designed into a real project matters far more than early deposits or revenue.\n\n### After the pause\n\nI think it’s fair to check that projects in Batch Zero are [what their developers swore](https://www.ercot.com/files/docs/2026/08/20/Batch-Zero-Verification-and-Audit-PUCT-Presentation.pdf) they are, and credible projects should move ahead soon. The permit freeze is harder to defend, though I see the state’s logic if the goal is to approve nothing until the audit is done. That said, I don’t like that it makes a developer that has funded its first phase, even one bringing its own power, wait like a speculator. Texas should narrow it now by exempting generators permitted only for emergencies and projects that have funded their first phase. The October 19 update to the governor from the state’s environmental regulator is the obvious place to start this conversation.\n\nOnce the review is done, the ongoing tests can be more straightforward. A developer that pays its security deposit, pays for the capacity it reserves, and hits phased milestones should get a connection date it can plan for. It should also connect sooner if it agrees to cut back when the grid is tight (Batch Zero [already does some of this](https://epeconsulting.com/epe-intelligence/news/new-pathway-and-deadlines-in-ercot-s-large-load-batch-zero-provisional-controllable-load-resource-pclr)). Going further, the utility building upgrades should probably answer for delays much like a developer does. Perhaps Texas [could](https://capitol.texas.gov/tlodocs/86R/analysis/pdf/SB01938F.pdf) [open lines to competitive bids](https://www.texasenergyandpower.com/p/texas-competes-on-everything-except) with cost caps and penalties.\n\nWhatever Texas decides, power will likely stay tight for years while the bottleneck keeps moving. Importantly, data centers are not that unique in the equipment they need; they just hit these limits first. In this sense, they’re the perfect rehearsal, because much of what we want to (re)build in this country will run on the same stuff.\n\nThat also makes it an opportunity I’d hate to waste. AI companies will pay nearly any price for power and can build almost anywhere, so they can help fund upgrades the grid needs anyway. Analyst Hans Royal estimates inference could pay an absurd [$5,600 per MWh](https://computeheatrate.com/chr-index) for power and still earn a decent return, nearly 60 times what [the average US industrial customer pays](https://www.eia.gov/electricity/monthly/update/end-use.php). That can strain local prices for gas, power, labor, and materials, but the infrastructure it funds can be worth far more. Admittedly, that argument can be a hard sell right now. In an August poll, [56% of Texas voters](https://texaspolitics.utexas.edu/blog/new-ut-texas-politics-project-poll-finds-talarico-leading-paxton-abbott-leading-hinojosa-continued-resistance-to-data-centers-2) said more data centers would hurt local energy bills.\n\nThe worry is fair since the honest answer is that it depends on who pays. In a perfect world, developers cover their upgrades and pay for the capacity they reserve, spreading the grid’s fixed costs across more sales so everyone else pays a smaller share. [Berkeley Lab found](https://eta-publications.lbl.gov/sites/default/files/2026-03/retail_price_trends_2026_edition.pdf) that from 2019 to 2025, the states with the most load growth generally saw average prices fall after inflation. Imagine all the money racing into AI helping the next factory connect and the next household electrify without an unaffordable bill (or a grid too tight for an EV, or a home robot). That household may never open a chatbot and still come away far better off. We’re already seeing early versions of this:\n\n- **Indiana:** The utility serving Amazon’s New Carlisle campus [proposed using data center revenue to cut household bills by about $100 a year](https://www.wvpe.org/wvpe-news/2026-08-26/i-m-announces-electric-rate-cut-plan-enabled-by-data-centers).\n- **Alabama:** A Tuscaloosa County campus will pay [$270 million in community benefits](https://yellowhammernews.com/tuscaloosa-county-lands-3-2-billion-data-center-first-in-alabama-to-pay-community-benefits-270-million-over-20-years/) over 20 years. In return, it gets about $314.5 million in tax breaks, though school taxes (about $131.5 million) aren’t abated.\n- **Pennsylvania:** One developer [offered every household in Hazle Township $10,000](https://www.yahoo.com/news/us/articles/data-center-developer-offers-10-114000653.html) if its campus gets approved, which some residents (perhaps correctly) called a bribe.\n\nI would not be surprised to see hyperscalers covering a whole town’s power bills as part of hosting a local campus. Most states, [Texas included](https://texas.public.law/statutes/tex._util._code_section_36.003), don’t let a utility single out one town, but at a small utility where data centers use most of the power, like [Oregon’s Umatilla Electric](https://www.cobank.com/knowledge-exchange/earning-the-business-by-demonstrating-network-value), covering a [typical household’s](https://www.eia.gov/electricity/sales_revenue_price/pdf/table_5A.pdf) bill for each of its [roughly 17,000 meters](https://www.umatillaelectric.com/about-us/who-we-are/) would only cost about $30 million a year. Such an agreement could pencil because that’s less than 0.5% of what a 1 GW campus [costs to own and run](https://epoch.ai/data-insights/ai-datacenter-cost-breakdown).\n\nIt’s also important to read the fine print when deals are made. In Arkansas, Google agreed to pay [$443 million](https://www.arkansasonline.com/news/2026/sep/03/googles-contribution-was-at-issue-in-arkansas/) up front toward an Entergy solar plant for its data center. The catch is that Entergy counted it as [prepayment for power](https://www.arkansasonline.com/news/2026/sep/03/googles-contribution-was-at-issue-in-arkansas/), so it can still seek the plant’s full cost plus a return from all its customers. And Entergy [sued two newspapers](https://www.cnbc.com/2026/09/02/google-data-center-arkansas-entergy-court.html) to stop them from reporting on the contract, then dropped the suit after a judge refused. Even if the deal is legal, this isn’t how you build trust with the community.\n\nA campus that levels with its neighbors and actually follows through keeps people on its side, and the next one gets easier to welcome. Get that wrong and everyone else can end up paying for it. In PJM, [the market monitor says data centers account for 38% of the latest capacity bill](https://www.utilitydive.com/news/pjm-data-centers-capacity-auction-imm-bowring/825626/), some $6.3 billion. Let me be clear: none of that justifies a blanket pause. But it does mean getting the rules and incentives right as we scale up development. AI companies have [pledged to pay their way](https://www.powermag.com/hyperscalers-sign-white-house-pledge-to-fund-data-center-power-grid-upgrades/), and most would rather connect to the grid than avoid it. It seems ideal for everyone that we let them do so instead of driving that spending into private islands, or pushing infrastructure upgrades that we’ll need anyway onto everyone else’s bills.\n\nTexas created the energy fast lane first; now it has the opportunity to show us a better one, and I expect it will. Power is where America finds out whether it can still build.\n\nIf you’re working on energy problems, I’d love to learn from you.\n","body_html":"<p>At the end of 2024, Texas’ grid operator had <a href=\"https://www.latitudemedia.com/news/ercots-large-load-queue-has-nearly-quadrupled-in-a-single-year/\" rel=\"nofollow ugc noopener\">63 GW of large new customers</a> in its queue. By this June, that <a href=\"https://www.utilitydive.com/news/texas-hits-pause-data-center-interconnections/827046/\" rel=\"nofollow ugc noopener\">figure reached 474 GW</a>, more than five times record peak demand, about 90% of it data centers.</p>\n<p>Then Texas <a href=\"https://www.texastribune.org/2026/08/03/texas-data-center-project-audit-greg-abbott/\" rel=\"nofollow ugc noopener\">hit pause</a>. What began as <a href=\"https://gov.texas.gov/news/post/governor-abbott-directs-puc-and-ercot-to-shield-texans-from-data-center-infrastructure-costs\" rel=\"nofollow ugc noopener\">directions</a> for data centers to pay for their own grid upgrades has since escalated to a <a href=\"https://gov.texas.gov/news/post/governor-abbott-directs-tceq-to-halt-data-center-permits\" rel=\"nofollow ugc noopener\">freeze</a> on all new permits. If you care about AI and American reindustrialization, this is important to understand. Why did it do this?</p>\n<p><a href=\"https://d1lamhf6l6yk6d.cloudfront.net/uploads/2026/10/How-Texas-Hit-Pause-on-Data-Centers-scaled.png\" rel=\"nofollow ugc noopener\"><img src=\"https://d1lamhf6l6yk6d.cloudfront.net/uploads/2026/10/How-Texas-Hit-Pause-on-Data-Centers-scaled.png\" alt=\"\" loading=\"lazy\" decoding=\"async\" referrerpolicy=\"no-referrer\" /></a></p>\n<p>The upcoming <a href=\"https://www.texastribune.org/2026/09/21/texas-data-center-moratorium-water-energy/\" rel=\"nofollow ugc noopener\">election</a> is part of it, but the underlying issues are worth digging into. The first is the interconnection queue. This pause is just as much about how projects apply for approval as it is about the projects themselves. Developers routinely spam projects across several sites, and many are <a href=\"https://www.bloomberg.com/news/articles/2026-08-12/most-electricity-sought-for-ai-data-centers-in-us-will-never-materialize\" rel=\"nofollow ugc noopener\">speculative</a> builds with no customer yet. Often these new developers have never even plugged in a GPU, let alone a power plant, so dealing with low-quality submissions puts ERCOT, which runs most of the state’s grid, in a <a href=\"https://www.texastribune.org/2026/06/17/texas-ercot-data-center-energy-grid/\" rel=\"nofollow ugc noopener\">tough spot</a>. Planners can’t tell which are real, and they don’t want ratepayers paying for upgrades built for projects that never show up.</p>\n<p><a href=\"https://d1lamhf6l6yk6d.cloudfront.net/uploads/2026/10/Little-of-Texass-Giant-Queue-has-Shown-Up-Yet-scaled.png\" rel=\"nofollow ugc noopener\"><img src=\"https://d1lamhf6l6yk6d.cloudfront.net/uploads/2026/10/Little-of-Texass-Giant-Queue-has-Shown-Up-Yet-scaled.png\" alt=\"\" loading=\"lazy\" decoding=\"async\" referrerpolicy=\"no-referrer\" /></a></p>\n<p>The second issue is community alignment. Noise, water, emissions, and power bills are <a href=\"https://www.pewresearch.org/short-reads/2026/09/22/americans-views-of-data-centers-have-turned-more-negative/\" rel=\"nofollow ugc noopener\">top of mind</a> for anyone who lives nearby. And regardless of the <a href=\"https://www.microsoft.com/en-us/microsoft-cloud/blog/2024/12/09/sustainable-by-design-next-generation-datacenters-consume-zero-water-for-cooling/\" rel=\"nofollow ugc noopener\">reality</a> of these issues, people deserve <a href=\"https://www.texastribune.org/2026/09/14/texas-data-centers-abbott-water-survey-enforcement/\" rel=\"nofollow ugc noopener\">straight answers</a> when a data center comes to town, and they <a href=\"https://www.ksat.com/news/texas/2026/08/10/while-data-centers-boom-in-texas-their-plans-stay-shrouded-in-secrecy/\" rel=\"nofollow ugc noopener\">haven’t always gotten them</a> (<a href=\"https://www.texastribune.org/2026/08/03/texas-data-center-project-audit-greg-abbott/\" rel=\"nofollow ugc noopener\">as of June, only 28 of 377 companies</a> had answered a state survey on their resource use). In Hood County, commissioners were asked to support a tax waiver for “Project Patriot” without knowing <a href=\"https://www.texastribune.org/2026/06/02/texas-data-centers-hood-county-local-control-rural-water-power/\" rel=\"nofollow ugc noopener\">who it was</a>. To be fair, code names are common while companies shop for sites since a famous buyer can drive up prices, but that logic becomes tougher to defend once officials vote on tax breaks.</p>\n<p>The broader political backdrop is important, but I’ll be focusing on the <a href=\"https://a16z.com/decentralizing-the-electric-grid/\" rel=\"nofollow ugc noopener\">energy</a> side: why it’s so hard to power a data center, all the ways developers are trying to do it anyway, and where things are likely headed.</p>\n<h3 id=\"what-connecting-to-the-grid-actually-means\">What connecting to the grid actually means</h3>\n<p>How Amazon purchases power helps illustrate what’s changed. For the last decade, they’d find a utility with network capacity, sign up as a large load, then enter long-term contracts to <a href=\"https://sustainability.aboutamazon.com/renewable-energy-methodology.pdf\" rel=\"nofollow ugc noopener\">match</a> their use on paper. These were often <a href=\"https://www.epa.gov/green-power-markets/financial-ppa\" rel=\"nofollow ugc noopener\">purely financial</a>, meaning you didn’t always have to prove the power could reach you, and the grid connection was easy because utilities had spare network capacity.</p>\n<p>That’s no longer true. The grid is stretched thin, and almost any new large load or generator now requires an upgrade. <a href=\"https://www.ferc.gov/sites/default/files/2020-05/ch1-3_0.pdf\" rel=\"nofollow ugc noopener\">Power flows across every connected path</a>, so buying from one plant doesn’t reserve a route to your building (there are even markets for transmission congestion <a href=\"https://www.ercot.com/mktinfo/crr\" rel=\"nofollow ugc noopener\">rights</a>).</p>\n<p><a href=\"https://d1lamhf6l6yk6d.cloudfront.net/uploads/2026/10/Every-plant-and-customer-shares-the-same-wires-scaled.png\" rel=\"nofollow ugc noopener\"><img src=\"https://d1lamhf6l6yk6d.cloudfront.net/uploads/2026/10/Every-plant-and-customer-shares-the-same-wires-scaled.png\" alt=\"\" loading=\"lazy\" decoding=\"async\" referrerpolicy=\"no-referrer\" /></a></p>\n<p>So buyers went after firm power (available around the clock) they could claim more directly, typically by <a href=\"https://www.constellationenergy.com/news/2024/Constellation-to-Launch-Crane-Clean-Energy-Center-Restoring-Jobs-and-Carbon-Free-Power-to-The-Grid.html\" rel=\"nofollow ugc noopener\">restarting retired plants</a> or by building next to existing ones. <a href=\"https://www.utilitydive.com/news/constellation-three-mile-island-crane-nuclear-ferc-waiver/821836/\" rel=\"nofollow ugc noopener\">Neither was a true escape</a>, and some of the loudest fights are over “colocation,” which <a href=\"https://www.ercot.com/files/docs/2026/06/01/ERCOT-Trending-Topic-Grid-Reliability-Data-Centers-Net-Metering-Arrangements.pdf\" rel=\"nofollow ugc noopener\">ERCOT describes</a> as drawing power from a neighboring plant before it reaches the grid:</p>\n<ul><li><strong>Susquehanna:</strong> Amazon <a href=\"https://www.ans.org/news/article-5842/amazon-buys-nuclearpowered-data-center-from-talen/\" rel=\"nofollow ugc noopener\">bought a campus</a> next to Talen’s nuclear plant, but FERC, the federal grid regulator, <a href=\"https://www.utilitydive.com/news/ferc-interconnection-isa-talen-amazon-data-center-susquehanna-exelon/731841/\" rel=\"nofollow ugc noopener\">rejected Talen’s bid</a> to send it more power directly. Utilities had argued it would let the campus dodge grid fees and push fixed transmission costs onto everyone else. After they <a href=\"https://www.sec.gov/Archives/edgar/data/1622536/000162253626000066/tln-20260630.htm\" rel=\"nofollow ugc noopener\">restructured the deal</a>, Amazon <a href=\"https://www.powermag.com/talen-amazon-launch-18b-nuclear-ppa-a-grid-connected-ipp-model-for-the-data-center-era/\" rel=\"nofollow ugc noopener\">pays for delivery like any other customer</a>.</li><li><strong>Freestone:</strong> CyrusOne’s 760 MW campus beside Constellation’s gas plant needed <a href=\"https://tcss.legis.texas.gov/resources/UT/htm/UT.39.htm#39.169\" rel=\"nofollow ugc noopener\">approval from the Public Utility Commission of Texas (PUCT)</a>, since it effectively takes much of the plant’s output from everyone else. The PUCT <a href=\"https://www.constellationenergy.com/news/2026/05/constellation-reports-first-quarter-2026-results.html\" rel=\"nofollow ugc noopener\">said yes</a> in May, as long as the campus can <a href=\"https://www.ercot.com/files/docs/2026/06/01/ERCOT-Trending-Topic-Grid-Reliability-Data-Centers-Net-Metering-Arrangements.pdf\" rel=\"nofollow ugc noopener\">cut its use</a> or switch to backup power within 30 minutes of an ERCOT call.</li><li><strong>Armstrong County:</strong> Two Crusoe data centers beside a wind farm got <a href=\"https://www.ercot.com/files/docs/2026/06/01/ERCOT-Trending-Topic-Grid-Reliability-Data-Centers-Net-Metering-Arrangements.pdf\" rel=\"nofollow ugc noopener\">the same rule</a>, and <a href=\"https://www.utilitydive.com/news/texas-approves-ai-data-center-co-location-next-to-wind-farm-with-curtailme/826617/\" rel=\"nofollow ugc noopener\">the second, approved in July</a>, must also shed its entire load, so together they’d cut nearly twice what the wind farm can produce.</li></ul>\n<p>Interconnection studies are how grid planners identify the wires and substations that need upgrades for any addition to the network. ERCOT used to review studies individually under rules <a href=\"https://www.utilitydive.com/news/ercots-large-load-queue-jumped-almost-300-last-year-official/808820/\" rel=\"nofollow ugc noopener\">built for 40 to 50 large loads at a time</a>, but 2025 brought 225 new requests by mid-November. So this June, the PUCT <a href=\"https://www.ercot.com/news/release/06182026-puct-approves-ercots\" rel=\"nofollow ugc noopener\">approved a new batch approach</a>. Under “Batch Zero,” ERCOT studies large loads of 75 MW or more together and allocates grid capacity among them.</p>\n<p>Primarily, the studies ask what happens when something breaks. <a href=\"https://www.nerc.com/pa/Stand/Reliability%20Standards/TPL-001-5.1.pdf\" rel=\"nofollow ugc noopener\">NERC’s standard</a>, the baseline for reliability across North America, covers a broad set of outage scenarios, with <a href=\"https://www.ercot.com/files/docs/2026/05/29/June-1-2026-Plannng-Guide.pdf\" rel=\"nofollow ugc noopener\">ERCOT adding its own requirements</a>. Planners might simulate a transformer outage, then knock out a line or generator on top of that. Maintaining that reliability standard without shedding more load often means building additional infrastructure.</p>\n<p><a href=\"https://d1lamhf6l6yk6d.cloudfront.net/uploads/2026/10/Two-lines-can-serve-an-area-comfortably-until-one-trips-scaled.png\" rel=\"nofollow ugc noopener\"><img src=\"https://d1lamhf6l6yk6d.cloudfront.net/uploads/2026/10/Two-lines-can-serve-an-area-comfortably-until-one-trips-scaled.png\" alt=\"\" loading=\"lazy\" decoding=\"async\" referrerpolicy=\"no-referrer\" /></a></p>\n<p>A newer risk is load dropping off the grid all at once. Many data centers switch to backup power at the first voltage dip to protect their hardware, so one bad fault can <a href=\"https://www.jdsupra.com/legalnews/nerc-computational-load-updates-6702832/\" rel=\"nofollow ugc noopener\">pull an enormous load</a> off the grid in seconds. This <a href=\"https://insidelines.pjm.com/pjm-dominion-review-large-load-transfer-event/\" rel=\"nofollow ugc noopener\">happened</a> earlier this year in Virginia, but was fortunately handled well.</p>\n<p>Texas has even less room for error since ERCOT’s grid is largely <a href=\"https://www.ercot.com/files/docs/2025/05/12/ERCOT-Grid-Insights-Electricity-Connection-and-Transfer.pdf\" rel=\"nofollow ugc noopener\">isolated</a>. Under some conditions, ERCOT can lose only <a href=\"https://www.ercot.com/files/docs/2026/09/16/QSA-Results-and-Large-Load-IROL-Mitigation-Plans_final.pdf\" rel=\"nofollow ugc noopener\">about 3.2 GW</a> of load at once before causing issues. A new voltage <a href=\"https://www.ercot.com/mktrules/issues/NOGRR282\" rel=\"nofollow ugc noopener\">ride-through rule</a> now requires new data centers to stay connected through routine faults, and I’ve even heard of labs running dummy jobs after a training run fails just to keep load from dropping abruptly.</p>\n<p><a href=\"https://d1lamhf6l6yk6d.cloudfront.net/uploads/2026/10/One-Virginia-line-failure-dropped-more-load-than-Texas-can-lose-at-once-scaled.png\" rel=\"nofollow ugc noopener\"><img src=\"https://d1lamhf6l6yk6d.cloudfront.net/uploads/2026/10/One-Virginia-line-failure-dropped-more-load-than-Texas-can-lose-at-once-scaled.png\" alt=\"\" loading=\"lazy\" decoding=\"async\" referrerpolicy=\"no-referrer\" /></a></p>\n<p>All of this can sound overly conservative, but the system was designed to put reliability ahead of cost. Put simply, the grid is built for the hot summer days and frigid winters when failure can mean life or death. That duty is what makes sizing the grid so hard; you build for a few peak hours but pay for it all year.</p>\n<p><a href=\"https://d1lamhf6l6yk6d.cloudfront.net/uploads/2026/10/The-grid-is-built-for-a-peak-it-neared-for-only-about-200-hours-scaled.png\" rel=\"nofollow ugc noopener\"><img src=\"https://d1lamhf6l6yk6d.cloudfront.net/uploads/2026/10/The-grid-is-built-for-a-peak-it-neared-for-only-about-200-hours-scaled.png\" alt=\"\" loading=\"lazy\" decoding=\"async\" referrerpolicy=\"no-referrer\" /></a></p>\n<p>So who does pay for all this resilience? Texas typically splits transmission costs by each large customer’s demand during the grid’s summer peaks, so a big load that ramps down on the hottest afternoons can skip much of its share of the transmission bill. In July, regulators <a href=\"https://interchange.puc.texas.gov/Documents/58000_8_1664102.PDF\" rel=\"nofollow ugc noopener\">proposed</a> counting all 12 monthly peaks instead and <a href=\"https://www.sos.texas.gov/texreg/archive/July242026/Proposed%20Rules/16.ECONOMIC%20REGULATION.html\" rel=\"nofollow ugc noopener\">charging</a> large loads as if they ran at full size. In other words, large buyers would pay in proportion to how big their electricity pipes need to be, not how much is flowing through them.</p>\n<p>Sounds simple enough, but splitting up costs is often the slowest part of interconnection. An upgrade built for one campus may also improve reliability for existing customers or make room for future growth that’s hard to value up front. And if any new development runs over budget or its load never shows up, everyone else is forced to cover whatever the developer’s commitments didn’t.</p>\n<p>And those commitments are surprisingly cheap to make. The PUCT’s <a href=\"https://interchange.puc.texas.gov/Documents/58481_218_1684654.PDF\" rel=\"nofollow ugc noopener\">new large-load rules</a>, effective October 8, charge a flat $100,000 study fee plus a $50,000-per-MW deposit. The deposit weeds out some speculative projects, but it’s a thin filter. ERCOT can reassign a project’s capacity if it falls two years behind, but even a project that loses its capacity forfeits just 20% of the deposit (at least $10 million on a 1 GW campus), plus whatever the utility has already spent. Most importantly, the deposit typically only backs the upgrades built for that project, not the more expensive regional lines whose cost everyone on the grid shares.</p>\n<p>Fully connecting a large data center can take <a href=\"https://arxiv.org/abs/2509.07218\" rel=\"nofollow ugc noopener\">5 to 10 years</a>. To accelerate deployment, a <a href=\"https://www.crusoe.ai/resources/newsroom/crusoe-expands-ai-data-center-campus-in-abilene-to-1-2-gigawatts\" rel=\"nofollow ugc noopener\">phased connection approach</a> is becoming <a href=\"https://www.sdxcentral.com/news/xai-colossus-memphis-power-tva/\" rel=\"nofollow ugc noopener\">more common</a>, which gives the utility more gradual targets to plan around, as well as a way for the developer to prove they can handle everything they’ve asked for. All of this also assumes Batch Zero is moving, which it isn’t right now. ERCOT has even <a href=\"https://www.ercot.com/files/docs/2026/08/20/Batch-Zero-Verification-and-Audit-PUCT-Presentation.pdf\" rel=\"nofollow ugc noopener\">paused approvals</a> for data centers of 75 MW or more to switch on, including 17 that had finished every other ERCOT step. Until the audit’s December report settles which projects are eligible, ERCOT can’t study them together, so the timeline is <a href=\"https://www.ercot.com/files/docs/2026/09/11/14-Batch-Zero-Update.pdf\" rel=\"nofollow ugc noopener\">“TBD”</a> and <a href=\"https://www.ercot.com/files/docs/2026/08/20/Batch-Zero-Verification-and-Audit-PUCT-Presentation.pdf\" rel=\"nofollow ugc noopener\">the load forecast is on hold</a>.</p>\n<h3 id=\"what-bringing-your-own-power-solves\">What bringing your own power solves</h3>\n<p>For a developer facing the interconnection queue, skipping the grid entirely looks appealing. Idle GPUs <a href=\"https://epoch.ai/data-insights/ai-datacenter-cost-breakdown\" rel=\"nofollow ugc noopener\">cost</a> far more than the electricity to run them, so speed matters most — what folks call “time to power.” That’s why developers are planning to bring their own power on site (“behind the meter”), but almost always alongside a connection to the grid, or as a bridge to one:</p>\n<ul><li><strong>Abilene:</strong> The Oracle campus <a href=\"https://www.crusoe.ai/resources/blog/an-inside-look-at-the-abilene-ai-data-center\" rel=\"nofollow ugc noopener\">runs on grid power with gas backup</a>. Next door, Crusoe announced a 900 MW Microsoft campus with its own <a href=\"https://www.crusoe.ai/resources/newsroom/crusoe-announces-new-900-mw-ai-factory-campus-in-abilene-texas-to-support-microsoft-ai-infrastructure\" rel=\"nofollow ugc noopener\">on-site plant</a>, but the CEO of Lancium, Crusoe’s partner on the site, has <a href=\"https://westtexastribune.org/2026/05/05/lancium-ceo-addresses-abilenes-concerns/\" rel=\"nofollow ugc noopener\">described gas generation as backup</a>.</li><li><strong>Shackelford County:</strong> Vantage is building a campus with 1.4 GW of compute for Oracle and OpenAI, designed to run off-grid on <a href=\"https://epoch.ai/publications/openai-stargate-where-the-us-sites-stand\" rel=\"nofollow ugc noopener\">on-site gas</a>. But <a href=\"https://records.tceq.texas.gov/cs/idcplg?IdcService=TCEQ_EXTERNAL_SEARCH_GET_FILE&amp;dID=8984027&amp;Rendition=Web\" rel=\"nofollow ugc noopener\">its site plan</a> includes a switchyard beside a high-voltage line — curious!</li><li><strong>Pecos County:</strong> Pacifico describes its planned microgrid (a behind-the-meter setup) at GW Ranch as <a href=\"https://www.pacificoenergy.com/gw-ranch\" rel=\"nofollow ugc noopener\">never drawing from ERCOT</a>, yet the site’s new owner, Amazon, says it’s <a href=\"https://www.aboutamazon.com/news/company-news/amazon-pecos-county-texas-data-center-clean-energy-jobs\" rel=\"nofollow ugc noopener\">designed to join the grid</a> once it can connect.</li><li><strong>West Texas:</strong> Under a <a href=\"https://www.chevron.com/newsroom/2026/q2/chevron-signs-20-year-power-agreement-with-microsoft-for-west-texas-data-center\" rel=\"nofollow ugc noopener\">20-year agreement</a>, Chevron plans to build a dedicated gas plant beside a planned Microsoft campus that won’t initially touch the ERCOT grid, though Chevron has applied for a connection. Chevron now says the permit freeze <a href=\"https://www.semafor.com/article/10/01/2026/texas-politics-could-delay-investment-decision-for-huge-chevron-data-center\" rel=\"nofollow ugc noopener\">could push its final investment decision into 2027</a>, but it still expects first power by 2028.</li><li><strong>Armstrong County:</strong> The Google campus Crusoe is building beside a wind farm is <a href=\"https://www.crusoe.ai/resources/newsroom/crusoe-developing-data-center-campus-in-armstrong-county-texas\" rel=\"nofollow ugc noopener\">tied to both the farm and the grid from day one</a>, with Crusoe calling it “<a href=\"https://www.crusoe.ai/resources/blog/co-located-power-for-ai-data-centers\" rel=\"nofollow ugc noopener\">across the meter</a>,” which I’ll admit is catchy.</li></ul>\n<p>SemiAnalysis is already tracking <a href=\"https://newsletter.semianalysis.com/p/everyone-says-datacenter-moratoriums\" rel=\"nofollow ugc noopener\">75 GW of equipment orders</a> for behind-the-meter assets, but every site I’m aware of intends to connect to the grid as soon as it can, chiefly because on-site power almost always costs more. So, once the grid is available, say in year five, you switch.</p>\n<p><a href=\"https://d1lamhf6l6yk6d.cloudfront.net/uploads/2026/10/Five-ways-a-campus-can-pair-its-own-power-with-the-grid-1-scaled.png\" rel=\"nofollow ugc noopener\"><img src=\"https://d1lamhf6l6yk6d.cloudfront.net/uploads/2026/10/Five-ways-a-campus-can-pair-its-own-power-with-the-grid-1-scaled.png\" alt=\"\" loading=\"lazy\" decoding=\"async\" referrerpolicy=\"no-referrer\" /></a></p>\n<p>In the meantime, pairing on-site assets with even a partial connection is smart for the same reasons we built a grid in the first place. When one plant trips, the rest of ERCOT’s <a href=\"https://www.ercot.com/files/docs/2022/02/08/ERCOT_Fact_Sheet.pdf\" rel=\"nofollow ugc noopener\">1,460-plus generating units</a> cover for it, but an islanded load (cut off from the grid) doesn’t have that luxury. The grid also provides things we take for granted, like <a href=\"https://www.osti.gov/biblio/1659820\" rel=\"nofollow ugc noopener\">inertia</a>, <a href=\"https://www.osti.gov/biblio/1870461\" rel=\"nofollow ugc noopener\">fault current</a>, steady voltage, and <a href=\"https://www.ercot.com/files/docs/2025/06/20/ERCOT-Grid-Insights-Black-Start.pdf\" rel=\"nofollow ugc noopener\">black start</a>. An island has to supply all of that itself — power systems folks know how hard this can be.</p>\n<p><a href=\"https://d1lamhf6l6yk6d.cloudfront.net/uploads/2026/10/An-island-has-to-build-what-the-grid-provides-scaled.png\" rel=\"nofollow ugc noopener\"><img src=\"https://d1lamhf6l6yk6d.cloudfront.net/uploads/2026/10/An-island-has-to-build-what-the-grid-provides-scaled.png\" alt=\"\" loading=\"lazy\" decoding=\"async\" referrerpolicy=\"no-referrer\" /></a></p>\n<p>AI workloads make the job even harder. At xAI’s first Memphis site, swings of 10 to 20 MW several times a second were <a href=\"https://newsletter.semianalysis.com/p/what-is-so-hard-about-behind-the\" rel=\"nofollow ugc noopener\">wearing out turbine shafts</a> until xAI added 150 MW of Tesla Megapacks. A grid ERCOT’s size dilutes swings like that, but on a private plant the turbines really feel it. Expect more batteries and other energy storage as rack-level power density grows and swings become more dramatic.</p>\n<p>Then there’s fueling a site. <a href=\"https://www.ercot.com/files/docs/2021/02/24/2.2_REVISED_ERCOT_Presentation.pdf\" rel=\"nofollow ugc noopener\">Winter Storm Uri’s</a> lesson is that gas plants can <a href=\"https://www.nerc.com/globalassets/standards/projects/2021-07/ferc-presentation-phase-2.pdf\" rel=\"nofollow ugc noopener\">fail together</a>. And since they tend to keep little fuel on site (NERC calls gas a <a href=\"https://www.nerc.com/globalassets/who-we-are/news/2025/10/2025-october-reliability-insights_final.pdf\" rel=\"nofollow ugc noopener\">“just-in-time” fuel</a>), spare turbines don’t always help. <a href=\"https://sourcenm.com/2026/08/17/proposed-gas-pipeline-for-project-jupiter-data-center-delayed-to-2027-filings-show/\" rel=\"nofollow ugc noopener\">Sometimes the pipeline doesn’t even exist yet</a>. Solar trades that fuel risk for the sun and weather, and at gigawatt scale, you need a lot of batteries. Keeping a 1 GW campus running through one 14-hour winter night takes 14 GWh from batteries, <a href=\"https://modoenergy.com/research/en/ercot-bess-buildout-16-gw-q2-2026-growth-slowing\" rel=\"nofollow ugc noopener\">about half of all the battery storage on ERCOT’s grid</a> as of June. For an island seeking 100% uptime, covering rare events like a cloudy week or another Uri gets expensive.</p>\n<p>Whatever the fuel, you want an island that fails gracefully and predictably, with no single point of failure. Even nuclear, about as reliable as power plants get, runs only about <a href=\"https://www.eia.gov/todayinenergy/detail.php?id=65904\" rel=\"nofollow ugc noopener\">92% of the time</a>, mostly because each reactor goes offline for weeks to refuel. Redundancy in this case means effectively an entire second power plant. Thus, behind-the-meter setups favor modularity, like the <a href=\"https://newsletter.semianalysis.com/p/what-is-so-hard-about-behind-the\" rel=\"nofollow ugc noopener\">more than 500 gas engines</a> of about 4 MW each planned for Shackelford, though hundreds of engines can be a pain to maintain.</p>\n<p>Full reliability for an island is very, very hard, but some labs and hyperscalers have shown that, forced to choose between reliability and speed, they’ll pick speed. Meta has turned to tents with <a href=\"https://newsletter.semianalysis.com/p/meta-superintelligence-leadership-compute-talent-and-data\" rel=\"nofollow ugc noopener\">no backup generators</a>, and SemiAnalysis finds buyers <a href=\"https://newsletter.semianalysis.com/p/what-is-so-hard-about-behind-the\" rel=\"nofollow ugc noopener\">growing more willing to accept outages</a>, with some island designs aiming for as little as 99% uptime, or about 88 hours of downtime a year. With <a href=\"https://newsletter.semianalysis.com/p/the-great-gpu-shortage-rental-capacity\" rel=\"nofollow ugc noopener\">GPU time this expensive</a>, that still beats years of waiting, so for many buyers a temporary island makes sense even if it’s messy.</p>\n<p>A “private grid” that ties several plants and campuses together can take back many of the benefits a lone island gives up, at least in theory. But today Texas, like most states, only allows building your own power within tight limits:</p>\n<ul><li><strong>Supplying yourself:</strong> You <a href=\"https://tcss.legis.texas.gov/resources/UT/htm/UT.31.htm\" rel=\"nofollow ugc noopener\">aren’t a utility</a> if you supply only yourself, your employees, or your tenants, and nobody resells the power.</li><li><strong>Running a private use network:</strong> You can also run on co-located generation, <a href=\"https://www.jdsupra.com/legalnews/private-use-networks-self-generation-4515203/\" rel=\"nofollow ugc noopener\">sell the surplus into the grid</a>, and draw from it when you fall short. This is the model for the Armstrong County campus, and for the West Texas one once it connects.<ul><li><strong>Selling to a neighbor:</strong> If you sell to the factory across the road, you need a <a href=\"https://www.puc.texas.gov/agency/rulesnlaws/subrules/electric/25.107/25.107.pdf\" rel=\"nofollow ugc noopener\">retail electric provider certificate</a>.</li><li><strong>Stringing a wire:</strong> Build your own line, and you’re probably running into the local utility’s <a href=\"https://www.puc.texas.gov/agency/rulesnlaws/subrules/electric/25.101/25.101.pdf\" rel=\"nofollow ugc noopener\">service territory</a>.</li></ul></li></ul>\n<p>The Cato Institute’s <a href=\"https://www.cato.org/briefing-paper/case-consumer-regulated-electricity-private-electricity-grids-offer-parallel-path\" rel=\"nofollow ugc noopener\">consumer-regulated electricity</a> proposal would loosen those limits by allowing private utilities to serve multiple customers across their own network. This isn’t an entirely new idea; Utah’s <a href=\"https://le.utah.gov/Session/2025/bills/enrolled/SB0132.pdf\" rel=\"nofollow ugc noopener\">SB 132</a> lets loads of 100 MW or more contract for a fully off-grid system. Texas currently doesn’t let a network like this serve multiple customers, but if the demand for power remains insatiable, I’d expect the more permissive states to win larger chunks of the buildout with this “Wild West” utility structure. (However, you may also risk a utility “<a href=\"https://www.utilitydive.com/news/as-data-centers-go-off-grid-utilities-face-new-cost-and-planning-risks/811944/\" rel=\"nofollow ugc noopener\">death spiral</a>,” with the grid’s fixed costs falling on fewer and fewer customers.)</p>\n<p>The flip side is a utility building the island itself. Outside ERCOT, El Paso Electric plans to put <a href=\"https://interchange.puc.texas.gov/Documents/59076_1_1564187.PDF\" rel=\"nofollow ugc noopener\">813 small gas generators from ERock</a> (366 MW in all) beside Meta’s new campus and run them as an island, on Meta’s dime, for up to five years. This is an option because, unlike the transmission and distribution utilities inside ERCOT, it still owns power plants. After the island period, it would connect the plant to its grid and could seek to spread the cost across all its customers, though in September administrative judges <a href=\"https://interchange.puc.texas.gov/Documents/59076_176_1686197.PDF\" rel=\"nofollow ugc noopener\">recommended</a> approval only if those customers are protected.</p>\n<p>Anything that runs on fuel also needs an air permit that matches how it operates, so a diesel generator permitted only for emergencies can’t run all the time. Optimistically, permits can <a href=\"https://newsletter.semianalysis.com/p/what-is-so-hard-about-behind-the\" rel=\"nofollow ugc noopener\">come fast</a> when things work. Sometimes they <a href=\"https://news.constructconnect.com/oracle-drops-gas-turbine-plan-for-its-massive-project-jupiter-turns-to-bloom-fuel-cells\" rel=\"nofollow ugc noopener\">don’t</a>, though. In Texas, the freeze now blocks them for data centers until the audit is done.</p>\n<p>We should also ask what instances of “bridge” gas are actually bridging to. xAI’s first two Memphis data centers answer that in different ways. The first ran temporary turbines off <a href=\"https://www.mlgw.com/images/content/files/pdf/new/xAI%202025%20Update.pdf\" rel=\"nofollow ugc noopener\">an existing gas main</a> until the grid arrived, then <a href=\"https://memphischamber.com/blog/press-release/xai-phase-one-substation-63-providing-150mw-of-power-to-facility/\" rel=\"nofollow ugc noopener\">began removing them</a>. Along the way, it <a href=\"https://www.selc.org/news/inside-memphis-fight-against-xai/\" rel=\"nofollow ugc noopener\">ran dozens without air permits</a>. For the second, xAI built its plant <a href=\"https://www.wsmv.com/2026/04/14/naacp-sues-xai-alleging-unlawful-operation-gas-turbines-southaven/\" rel=\"nofollow ugc noopener\">across the state line</a> in Southaven, Mississippi, but a July order <a href=\"https://tippahnews.com/mississippi-news/mississippi-sets-retirement-schedule-for-xai-turbines-allows-some-to-run-past-deadline/\" rel=\"nofollow ugc noopener\">requires all 69 turbines to retire</a> by mid-2027 as a permanent 1.2 GW plant goes up in their place. One bridge led to the grid, and the other to a power plant of xAI’s own.</p>\n<p>In August, though, the federal Tennessee Valley Authority (TVA) <a href=\"https://www.aol.com/articles/tva-board-approves-agreement-spacexai-234602000.html\" rel=\"nofollow ugc noopener\">agreed</a> to serve that data center directly, too. Turns out it’s hard to stay away from the grid!</p>\n<h3 id=\"what-flexibility-can-buy\">What flexibility can buy</h3>\n<p>A campus that can keep itself running can also be easier for the grid to accommodate, even welcome. It’s a large paying customer whose demand can “flex” when power is tight, whether by cutting its draw or exporting surplus power. This is how xAI got approved for grid power at its second Memphis site. What made its promise to flex credible was its ability to carry its entire load for four hours on its own power, and what the CEO of Memphis Light, Gas and Water called <a href=\"https://www.canarymedia.com/articles/batteries/xai-massive-battery-memphis-data-center\" rel=\"nofollow ugc noopener\">“the world’s largest grid-connected battery system.”</a></p>\n<p>Batteries are only one way to flex. A campus can also <a href=\"https://cloud.google.com/blog/products/infrastructure/using-demand-response-to-reduce-data-center-power-consumption\" rel=\"nofollow ugc noopener\">shift computing</a> to other hours or data centers, or switch to its own generators. So how much room could flexibility open up? <a href=\"https://nicholasinstitute.duke.edu/publications/rethinking-load-growth\" rel=\"nofollow ugc noopener\">Tyler Norris and colleagues at Duke</a> estimated that, setting transmission limits aside, ERCOT could add about 10 GW of new load without new generation if that load gave up 0.5% of its yearly grid electricity. Since the average cutback lasts about two hours, it’s also conveniently battery-shaped. Building on this, a <a href=\"https://www.camus.energy/flexible-data-center-report\" rel=\"nofollow ugc noopener\">study of PJM (the largest US power market) by Camus, encoord, and Princeton</a> found that for each GW of new data center load, making 20% of that load flexible would save other customers $78 million a year, while bringing its own capacity for the other 80% would keep another $326 million off their bills.</p>\n<p><a href=\"https://d1lamhf6l6yk6d.cloudfront.net/uploads/2026/10/Flexible-campuses-could-add-about-100-GW-without-new-power-plants-1-scaled.png\" rel=\"nofollow ugc noopener\"><img src=\"https://d1lamhf6l6yk6d.cloudfront.net/uploads/2026/10/Flexible-campuses-could-add-about-100-GW-without-new-power-plants-1-scaled.png\" alt=\"\" loading=\"lazy\" decoding=\"async\" referrerpolicy=\"no-referrer\" /></a></p>\n<p>For flexibility to be valuable, it’s important that it’s always available when operators need it. In Texas, generators already work this way under <a href=\"https://www.utilitydive.com/news/connect-and-manage-grid-interconnection-ferc-ercot-transmission-planning/698949/\" rel=\"nofollow ugc noopener\">connect-and-manage</a>. Put simply, they can hook up early as long as ERCOT can cut them down when lines are congested. Generators can live with that because at worst they sell less for a while, but a data center that has promised its customers uptime is more challenging. Some loads, like <a href=\"https://www.cnbc.com/2023/09/06/texas-paid-bitcoin-miner-riot-31point7-million-to-shut-down-in-august.html\" rel=\"nofollow ugc noopener\">Bitcoin miners</a>, have made the trade anyway. <a href=\"https://www.ercot.com/files/docs/2026/06/18/ERCOT-Trending-Topic-New-Batch-Connection-Process-for-Large-Electricity-Users.pdf\" rel=\"nofollow ugc noopener\">Batch Zero</a> gives large loads two optional paths here:</p>\n<ul><li><strong>Bring your own power:</strong> A campus can count its own power plant toward its size as long as it can cut back within <a href=\"https://www.willkie.com/publications/2026/06/ercot-approves-implementing-new-batch-zero-process-for-large-load-interconnections\" rel=\"nofollow ugc noopener\">one minute</a> if the plant fails. So far, 11 Batch Zero projects have picked this path.</li><li><strong>Agree to cuts:</strong> A campus can draw up to the full amount it asked for, but ERCOT can automatically cut anything above its guaranteed share whenever lines are full.</li></ul>\n<p><a href=\"https://d1lamhf6l6yk6d.cloudfront.net/uploads/2026/10/Two-ways-to-connect-more-than-the-grid-%E2%80%A8can-guarantee-scaled.png\" rel=\"nofollow ugc noopener\"><img src=\"https://d1lamhf6l6yk6d.cloudfront.net/uploads/2026/10/Two-ways-to-connect-more-than-the-grid-%E2%80%A8can-guarantee-scaled.png\" alt=\"\" loading=\"lazy\" decoding=\"async\" referrerpolicy=\"no-referrer\" /></a></p>\n<p>A campus could also pay its neighbors to cut their load instead. In PJM, <a href=\"https://www.utilitydive.com/news/google-virtual-power-plant-vpp-pjm-voltus/821838/\" rel=\"nofollow ugc noopener\">Google is funding Voltus</a> to pool up to 100 MW of batteries, thermostats, and other flexible devices across a territory. But PJM only counts what it trusts the pool to deliver, and it’s a <a href=\"https://www.latitudemedia.com/news/google-is-voltus-first-bring-your-own-capacity-customer/\" rel=\"nofollow ugc noopener\">capacity deal</a> that helps the whole grid at its peak, not a fix for any one congested line. That’s a harder sell in Texas, an energy-only market where transmission is the main bottleneck. Texas has also <a href=\"https://interchange.puc.texas.gov/Documents/58881_105_1628395.PDF\" rel=\"nofollow ugc noopener\">barred</a> colocated campuses from getting paid for <a href=\"https://interchange.puc.texas.gov/Documents/59220_69_1668205.PDF\" rel=\"nofollow ugc noopener\">similar services</a>, since under <a href=\"https://www.utilitydive.com/news/texas-law-gives-grid-operator-power-to-disconnect-data-centers-during-crisi/751587/\" rel=\"nofollow ugc noopener\">SB 6</a> they already have to shut off when ERCOT tells them.</p>\n<p>Even so, Texas has been a leader in distributed resources. One <a href=\"https://www.gvec.org/gvec-and-base-power-partnership/\" rel=\"nofollow ugc noopener\">Base Power fleet, run with the co-op GVEC</a>, passed ERCOT’s pilot tests to sell directly into the wholesale market on its first attempt, and is now expanding to 50 MW. These pilots are important; planners need that kind of proof before they’ll design around these fleets. But once trusted, distributed resources can rapidly add capacity without waiting for an expensive new “<a href=\"https://en.wikipedia.org/wiki/Peaking_power_plant\" rel=\"nofollow ugc noopener\">peaker</a>” power plant, lines, substations, or a lengthy interconnection process.</p>\n<p>Other hardware can help, too. Unlike legacy steel units, a solid-state transformer uses semiconductor switches, so software can measure and steer the power flowing through it. Alongside network upgrades like reconductoring (restringing lines with higher-capacity wire) and dynamic line ratings (rating lines for actual weather instead of worst-case conditions), that greater visibility and control can squeeze more out of wires ratepayers already funded. It’s a big reason we backed <a href=\"https://a16z.com/announcement/investing-in-heron-power/\" rel=\"nofollow ugc noopener\">Heron Power</a>, which is set to install its solid-state transformers at a <a href=\"https://www.globenewswire.com/news-release/2026/09/21/3365509/0/en/heron-power-and-rwe-sign-pilot-agreement-outline-path-to-multi-year-capacity-reservation.html\" rel=\"nofollow ugc noopener\">West Texas battery site with RWE</a>.</p>\n<p>The problem is that most of these tools help operators keep things running day to day, but planners don’t always count them when they size upgrades. Nothing in physics forces that, though. A September <a href=\"https://www.piqenergy.com/research/piq-energy-base-power---flexibility-without-curtailment.pdf\" rel=\"nofollow ugc noopener\">study by Piq Energy</a>, using <a href=\"https://a16z.com/announcement/investing-in-base-power/\" rel=\"nofollow ugc noopener\">Base Power</a>’s data on potential fleets, found that about 80 MW of home batteries, strategically sited to relieve transmission constraints, could resolve all overloads triggered by a hypothetical new 100 MW data center near Fort Worth.</p>\n<p>Batch Zero doesn’t consider things like this yet. It <a href=\"https://epeconsulting.com/epe-intelligence/news/new-pathway-and-deadlines-in-ercot-s-large-load-batch-zero-provisional-controllable-load-resource-pclr\" rel=\"nofollow ugc noopener\">still plans upgrades for a flexible campus’s full planned load</a>, since that path is a bridge to firm service, and there’s no option to stay flexible for good in exchange for smaller upgrades. Flexibility gets a campus connected sooner, but it doesn’t shrink the upgrades. Planners could instead size them smaller by crediting flexibility and other resources that relieve the same bottleneck, assuming they’re measured in real time and perform reliably.</p>\n<p>All of this saves time and money by getting more out of what’s already in the ground, but no amount of flexibility gets the grid out of building more generation and wires for all the demand coming down the pipe.</p>\n<h3 id=\"getting-to-hundreds-of-gigawatts\">Getting to hundreds of gigawatts</h3>\n<p>On-site power and flexibility will decide how the next few campuses energize, but the labs and hyperscalers I talk to worry most about scale. Their power teams tend to split in two: one picks sites and equipment for the next couple of years, and the other asks how to connect hundreds more gigawatts after 2030.</p>\n<p>This is a lot! Run, say, 100 GW all year and it’s 876 TWh, <a href=\"https://www.eia.gov/energyexplained/electricity/use-of-electricity.php\" rel=\"nofollow ugc noopener\">about a fifth</a> of what the country used in 2025. Here’s what power developers <a href=\"https://www.eia.gov/todayinenergy/detail.php?id=67205\" rel=\"nofollow ugc noopener\">told the Energy Information Administration</a> (EIA) they planned to add in 2026 across the entire grid.</p>\n<p><a href=\"https://d1lamhf6l6yk6d.cloudfront.net/uploads/2026/10/Most-new-grid-capacity-planned-for-2026-is-solar-and-batteries-scaled.png\" rel=\"nofollow ugc noopener\"><img src=\"https://d1lamhf6l6yk6d.cloudfront.net/uploads/2026/10/Most-new-grid-capacity-planned-for-2026-is-solar-and-batteries-scaled.png\" alt=\"\" loading=\"lazy\" decoding=\"async\" referrerpolicy=\"no-referrer\" /></a></p>\n<p>Every source helps, and much of it is headed to Texas anyway. But at last year’s average capacity factors (how much plants actually produce versus their maximum), the planned <a href=\"https://www.eia.gov/electricity/monthly/epm_table_grapher.php?t=epmt_6_07_b\" rel=\"nofollow ugc noopener\">solar, wind</a>, and <a href=\"https://www.eia.gov/electricity/monthly/epm_table_grapher.php?t=epmt_6_07_a\" rel=\"nofollow ugc noopener\">gas plants</a> would make around 150 TWh a year, or about a sixth of that 876 TWh.</p>\n<p>To be fair, that gas bar likely understates <a href=\"https://www.distilled.earth/p/eight-new-gas-plants-will-power-amazons\" rel=\"nofollow ugc noopener\">what’s being built</a>, since <a href=\"https://www.eia.gov/survey/form/eia_860/instructions.pdf\" rel=\"nofollow ugc noopener\">EIA’s survey only counts plants tied to the grid</a>. In this way, much of the 75 GW of on-site power equipment already on order could be ghost capacity that charts like this one will miss. Still, gas remains popular because it generally runs whenever you need it. And because of that, the constraint is mostly <a href=\"https://www.sec.gov/Archives/edgar/data/0001996810/000199681026000147/gevpressrelease2q26.htm\" rel=\"nofollow ugc noopener\">getting the equipment</a> in the first place, so buyers are turning to alternatives that can be <a href=\"https://www.latitudemedia.com/news/is-the-gas-turbine-bottleneck-solving-itself/\" rel=\"nofollow ugc noopener\">easier to find</a>, like <a href=\"https://www.powermag.com/data-centers-are-turning-to-gas-generators-for-prime-power-to-eliminate-long-lead-times-for-grid-connections/\" rel=\"nofollow ugc noopener\">reciprocating engines</a> and <a href=\"https://investor.bloomenergy.com/press-releases/press-release-details/2026/Bloom-Energy-and-Oracle-Expand-Strategic-Partnership-to-Deploy-up-to-2-8-GW-to-Accelerate-AI-Infrastructure-Build-Out/default.aspx\" rel=\"nofollow ugc noopener\">fuel cells</a>.</p>\n<p>That said, gas feels like an incomplete answer to me. I’m no Greenpeace warrior, but running 100 GW around the clock at gas plants’ <a href=\"https://www.eia.gov/tools/faqs/faq.php?id=74&amp;t=11\" rel=\"nofollow ugc noopener\">average rate</a> would release nearly 8% of the country’s <a href=\"https://www.eia.gov/environment/emissions/carbon/\" rel=\"nofollow ugc noopener\">energy-related emissions</a>. Often the easiest equipment to get is even <a href=\"https://www.eia.gov/electricity/annual/html/epa_08_02.html\" rel=\"nofollow ugc noopener\">less efficient</a>, too.</p>\n<p><a href=\"https://d1lamhf6l6yk6d.cloudfront.net/uploads/2026/10/Running-100-GW-on-gas-would-burn-more-Gas-than-the-US-exported-as-LNG-in-2025-scaled.png\" rel=\"nofollow ugc noopener\"><img src=\"https://d1lamhf6l6yk6d.cloudfront.net/uploads/2026/10/Running-100-GW-on-gas-would-burn-more-Gas-than-the-US-exported-as-LNG-in-2025-scaled.png\" alt=\"\" loading=\"lazy\" decoding=\"async\" referrerpolicy=\"no-referrer\" /></a></p>\n<p>Solar is compelling because it already has the production scale the labs are aiming for. The problem is that it’s mostly in China. The world <a href=\"https://www.solarpowereurope.org/press-releases/new-report-global-solar-market-hits-new-record-of-664-gw-installation-in-2025-as-global-solar-fleet-passes-3-tw\" rel=\"nofollow ugc noopener\">added more than 600 GW</a> in 2025, but China alone makes <a href=\"https://www.iea.org/reports/solar-pv-global-supply-chains/executive-summary\" rel=\"nofollow ugc noopener\">more than 80% of the world’s solar components</a> and <a href=\"https://www.iea.org/reports/global-ev-outlook-2026/manufacturing-and-trade\" rel=\"nofollow ugc noopener\">battery cells</a>. From what I can tell, Chinese suppliers don’t mind selling to us that much, at least partly because they see our scale-up as “cute.” However, China <a href=\"https://finance.yahoo.com/sectors/energy/articles/exclusive-china-weighs-curbs-exports-074947904.html\" rel=\"nofollow ugc noopener\">reportedly weighed</a> curbing exports of specific solar manufacturing equipment. Washington has also put on pressure, with <a href=\"https://pv-magazine-usa.com/2022/11/11/due-to-forced-labor-concerns-u-s-ports-have-blocked-over-1000-shipments-of-solar-components/\" rel=\"nofollow ugc noopener\">forced-labor shipment holds</a>, <a href=\"https://pv-magazine-usa.com/2026/08/07/us-announces-tariffs-minimum-import-price-on-polysilicon-imports/\" rel=\"nofollow ugc noopener\">new tariffs</a>, and <a href=\"https://www.irs.gov/pub/irs-drop/n-25-42.pdf\" rel=\"nofollow ugc noopener\">phasing out wind and solar credits</a>. Despite this, Elon is aiming <a href=\"https://pv-magazine-usa.com/2026/01/26/elon-musk-at-wef-spacex-and-tesla-to-produce-100-gw-each-of-pv-per-year-in-the-u-s-this-decade/\" rel=\"nofollow ugc noopener\">for 200 GW a year</a> of US solar manufacturing on his own, <a href=\"https://x.com/elonmusk/status/1925872357781983522?s=20\" rel=\"nofollow ugc noopener\">obviously</a> solar-pilled.</p>\n<p>Scaling firm power that isn’t gas is much more complicated. <a href=\"https://www.prnewswire.com/news-releases/georgia-power-agreement-with-google-to-provide-approximately-900-million-in-projected-benefits-for-customers-and-advance-nuclear-energy-in-georgia-302885197.html\" rel=\"nofollow ugc noopener\">Uprates</a> and restarts can <a href=\"https://www.reuters.com/business/energy/google-enters-massive-36-gw-power-deal-with-constellation-energy-2026-10-06/\" rel=\"nofollow ugc noopener\">squeeze</a> a little more from the existing nuclear fleet, but the real upside is new reactors, as <a href=\"https://a16z.com/how-to-scale-nuclear-power/\" rel=\"nofollow ugc noopener\">we’ve argued before</a>. <a href=\"https://about.fb.com/news/2026/01/meta-nuclear-energy-projects-power-american-ai-leadership/\" rel=\"nofollow ugc noopener\">Meta</a> and <a href=\"https://www.aboutamazon.com/news/sustainability/amazon-smr-nuclear-energy\" rel=\"nofollow ugc noopener\">Amazon</a> have signed big deals, but much of it is still options and targets. So far, the military has been a stronger <a href=\"https://breakingdefense.com/2026/08/army-taps-5-vendors-to-build-nuclear-microreactors-with-2-2b-pot/\" rel=\"nofollow ugc noopener\">buyer</a> to build microreactors on its bases, which is how factory-built reactors can learn to get faster and cheaper (blame EPC as much as the NRC). Geothermal could also leverage drilling (something Texas knows well) for repeatable power — <a href=\"https://fervoenergy.com/fervo-energy-and-google-sign-396-mw-ppa/\" rel=\"nofollow ugc noopener\">Google</a> and <a href=\"https://www.businesswire.com/news/home/20240826755596/en/Sage-Geosystems-and-Meta-Announce-Agreement-for-Next-Generation-Geothermal-Power-Generation\" rel=\"nofollow ugc noopener\">Meta</a> appear quite interested.</p>\n<p>Regardless of the power source, it all still ends up waiting on other equipment like transformers and switchgear, and all the crews to install them. Large power transformers now take <a href=\"https://www.powermag.com/transformers-in-2026-shortage-scramble-or-self-inflicted-crisis/\" rel=\"nofollow ugc noopener\">more than two years</a> to arrive, and the FCC has <a href=\"https://docs.fcc.gov/public/attachments/DA-26-786A1.pdf\" rel=\"nofollow ugc noopener\">limited new foreign-made inverters</a> alongside an <a href=\"https://www.whitehouse.gov/presidential-actions/2026/08/declaring-a-national-emergency-to-secure-the-united-states-bulk-power-system/\" rel=\"nofollow ugc noopener\">August emergency order</a> that could further bar Chinese-made equipment from the grid.</p>\n<p>Someone also has to build the wires. In 2008, Texas regulators ordered the <a href=\"https://www.bakerinstitute.org/sites/default/files/2020-11/import/ces-pub-texascrez-111720.pdf\" rel=\"nofollow ugc noopener\">CREZ lines</a> to carry West Texas wind, then spread their $7 billion cost across every ratepayer. Now they’re approving even bigger <a href=\"https://www.texastribune.org/2026/08/28/transmission-lines-texas-energy/\" rel=\"nofollow ugc noopener\">765 kV lines</a>, but it’s going <a href=\"https://thetexan.news/issues/energy/here-s-the-current-state-of-the-plan-to-build-765-kv-transmission-lines-across/article_b7e8c5bb-35c7-42d7-bed9-04f243de1927.html\" rel=\"nofollow ugc noopener\">slower</a> than many would like. Some of that is just (unfortunately) typical construction, which is slow and expensive anywhere, but there’s also a myriad of additional regulatory hurdles on top. The <a href=\"https://www.energy.senate.gov/press/rep/lee-capito-heinrich-and-whitehouse-introduce-bipartisan-american-affordability-and-jobs-act-of-2026/\" rel=\"nofollow ugc noopener\">federal permitting deal taking shape in Washington</a> could help move things along if Congress can pass it.</p>\n<p>Admittedly, I’m more confident that we’ll need a lot of power than I am about the exact shape it takes. My bet is that a handful of setups, depending on geography and flexibility, get built over and over. Maybe on-site gas and batteries carry a campus until its grid connection shows up, then stick around as backup to flex when the grid is tight. Solar gets layered on now where it fits, and geothermal and reactors come in once they prove out.</p>\n<p>Past 2030, it’s even harder to say who ends up building and owning all that power. One answer is that the same company builds both the plant and the campus (vertical integration), which Google’s <a href=\"https://abc.xyz/investor/news/news-details/2025/Alphabet-Announces-Agreement-to-Acquire-Intersect-to-Advance-U-S--Energy-Innovation-2025-DVIuVDM9wW/default.aspx\" rel=\"nofollow ugc noopener\">purchase of Intersect</a> may signal. Another is that oil and gas companies, like Chevron or Williams, become <a href=\"https://travisfisher.substack.com/p/socrates-south-shows-the-benefits\" rel=\"nofollow ugc noopener\">broader grid builders</a>, and it isn’t hard to picture them, or “neo-utilities” like NRG and NextEra, building private grids that serve several campuses, assuming the law enables it.</p>\n<p>I don’t know which way it goes yet, but they’ll all be buying from the same equipment makers. That market is huge and surprisingly ill-equipped to meet inflecting demand. Given that, I see two major ways for startups to break in:</p>\n<ul><li><strong>Integration:</strong> Some take familiar hardware and win on integration or business model, the way Base Power runs home batteries as a trusted aggregated resource.</li><li><strong>Technology:</strong> Others bring new technology so much better that early adopters will take a chance on it, which is what Heron Power is aiming to do with solid-state transformers.</li></ul>\n<p>A third pitch, crudely put as “worse but faster,” sells well in a shortage, but I’d ask what those profits are being reinvested in, because it might get hard to compete if broader supply catches up.</p>\n<p>Indeed, shortages like these are an opening for startups, but it helps to understand why incumbents aren’t quick to fill them. The last bet on a turbine boom ended in a $22 billion GE Power write-down and <a href=\"https://www.bostonglobe.com/business/2018/10/01/john-flannery-out-general-electric-ceo/7QRPwEHxACP1PON92Vq8WJ/story.html\" rel=\"nofollow ugc noopener\">helped cost GE’s CEO his job</a>. A startup has to survive the busts incumbents are planning around, as well as compete globally with Siemens Energy, Mitsubishi Power, and all sorts of suppliers in places like India and China. Customers may pay for speed today, but keeping them will take reliable, competitively priced equipment and a service team that knows what it’s doing.</p>\n<p>Every step of site development is hard. Vendors like GE Vernova now take <a href=\"https://www.gevernova.com/sites/default/files/gev_webcast_transcript_10222025.pdf\" rel=\"nofollow ugc noopener\">nonrefundable deposits</a> just to reserve a manufacturing slot, leaving developers with a <a href=\"https://newsletter.semianalysis.com/p/what-is-so-hard-about-behind-the\" rel=\"nofollow ugc noopener\">chicken-and-egg problem</a>. Lenders want a long-term contract with a solid customer, who wants a credible timeline, and that timeline takes deposits the developer usually needs lenders to fund. Bring in an unproven vendor and the loop gets even harder to close (and markets notice fast when it <a href=\"https://amarillotribune.org/2025/12/12/fermi-stock-drops-after-termination-of-150-million-construction-agreement/\" rel=\"nofollow ugc noopener\">breaks</a>). Once it closes, everything else still <a href=\"https://www.bloomberg.com/news/articles/2026-09-24/oracle-cites-force-majeure-to-shield-itself-on-controversial-data-center\" rel=\"nofollow ugc noopener\">has to go right</a>.</p>\n<p>For a new vendor, even getting into a campus’s first phase is difficult. Hardly anyone has placed a large, firm order for data center power equipment without thousands of hours of operation. For example, <a href=\"https://www.globenewswire.com/news-release/2026/07/22/3331360/35538/en/ftai-announces-1-465-billion-gas-turbine-generator-set-order-through-j-f-power-systems.html\" rel=\"nofollow ugc noopener\">FTAI’s big order</a> rests on the CFM56, a jet engine that has logged <a href=\"https://www.safran-group.com/pressroom/cfm56-engine-fleet-surpasses-one-billion-engine-flight-hours-2019-06-04\" rel=\"nofollow ugc noopener\">more than a billion flight hours</a>, while Crusoe <a href=\"https://techcrunch.com/2026/09/25/crusoe-abandons-1-25b-plan-to-use-boom-turbines-at-ai-data-centers/\" rel=\"nofollow ugc noopener\">stepped back from Boom</a> as Boom’s first engine core was still <a href=\"https://aviationweek.com/business-aviation/aircraft-propulsion/boom-supersonic-gears-engine-prototype-core-testing\" rel=\"nofollow ugc noopener\">gearing up for tests</a>. So even credible teams building awesome technology face a cold-start problem. Thus, getting your product designed into a real project matters far more than early deposits or revenue.</p>\n<h3 id=\"after-the-pause\">After the pause</h3>\n<p>I think it’s fair to check that projects in Batch Zero are <a href=\"https://www.ercot.com/files/docs/2026/08/20/Batch-Zero-Verification-and-Audit-PUCT-Presentation.pdf\" rel=\"nofollow ugc noopener\">what their developers swore</a> they are, and credible projects should move ahead soon. The permit freeze is harder to defend, though I see the state’s logic if the goal is to approve nothing until the audit is done. That said, I don’t like that it makes a developer that has funded its first phase, even one bringing its own power, wait like a speculator. Texas should narrow it now by exempting generators permitted only for emergencies and projects that have funded their first phase. The October 19 update to the governor from the state’s environmental regulator is the obvious place to start this conversation.</p>\n<p>Once the review is done, the ongoing tests can be more straightforward. A developer that pays its security deposit, pays for the capacity it reserves, and hits phased milestones should get a connection date it can plan for. It should also connect sooner if it agrees to cut back when the grid is tight (Batch Zero <a href=\"https://epeconsulting.com/epe-intelligence/news/new-pathway-and-deadlines-in-ercot-s-large-load-batch-zero-provisional-controllable-load-resource-pclr\" rel=\"nofollow ugc noopener\">already does some of this</a>). Going further, the utility building upgrades should probably answer for delays much like a developer does. Perhaps Texas <a href=\"https://capitol.texas.gov/tlodocs/86R/analysis/pdf/SB01938F.pdf\" rel=\"nofollow ugc noopener\">could</a> <a href=\"https://www.texasenergyandpower.com/p/texas-competes-on-everything-except\" rel=\"nofollow ugc noopener\">open lines to competitive bids</a> with cost caps and penalties.</p>\n<p>Whatever Texas decides, power will likely stay tight for years while the bottleneck keeps moving. Importantly, data centers are not that unique in the equipment they need; they just hit these limits first. In this sense, they’re the perfect rehearsal, because much of what we want to (re)build in this country will run on the same stuff.</p>\n<p>That also makes it an opportunity I’d hate to waste. AI companies will pay nearly any price for power and can build almost anywhere, so they can help fund upgrades the grid needs anyway. Analyst Hans Royal estimates inference could pay an absurd <a href=\"https://computeheatrate.com/chr-index\" rel=\"nofollow ugc noopener\">$5,600 per MWh</a> for power and still earn a decent return, nearly 60 times what <a href=\"https://www.eia.gov/electricity/monthly/update/end-use.php\" rel=\"nofollow ugc noopener\">the average US industrial customer pays</a>. That can strain local prices for gas, power, labor, and materials, but the infrastructure it funds can be worth far more. Admittedly, that argument can be a hard sell right now. In an August poll, <a href=\"https://texaspolitics.utexas.edu/blog/new-ut-texas-politics-project-poll-finds-talarico-leading-paxton-abbott-leading-hinojosa-continued-resistance-to-data-centers-2\" rel=\"nofollow ugc noopener\">56% of Texas voters</a> said more data centers would hurt local energy bills.</p>\n<p>The worry is fair since the honest answer is that it depends on who pays. In a perfect world, developers cover their upgrades and pay for the capacity they reserve, spreading the grid’s fixed costs across more sales so everyone else pays a smaller share. <a href=\"https://eta-publications.lbl.gov/sites/default/files/2026-03/retail_price_trends_2026_edition.pdf\" rel=\"nofollow ugc noopener\">Berkeley Lab found</a> that from 2019 to 2025, the states with the most load growth generally saw average prices fall after inflation. Imagine all the money racing into AI helping the next factory connect and the next household electrify without an unaffordable bill (or a grid too tight for an EV, or a home robot). That household may never open a chatbot and still come away far better off. We’re already seeing early versions of this:</p>\n<ul><li><strong>Indiana:</strong> The utility serving Amazon’s New Carlisle campus <a href=\"https://www.wvpe.org/wvpe-news/2026-08-26/i-m-announces-electric-rate-cut-plan-enabled-by-data-centers\" rel=\"nofollow ugc noopener\">proposed using data center revenue to cut household bills by about $100 a year</a>.</li><li><strong>Alabama:</strong> A Tuscaloosa County campus will pay <a href=\"https://yellowhammernews.com/tuscaloosa-county-lands-3-2-billion-data-center-first-in-alabama-to-pay-community-benefits-270-million-over-20-years/\" rel=\"nofollow ugc noopener\">$270 million in community benefits</a> over 20 years. In return, it gets about $314.5 million in tax breaks, though school taxes (about $131.5 million) aren’t abated.</li><li><strong>Pennsylvania:</strong> One developer <a href=\"https://www.yahoo.com/news/us/articles/data-center-developer-offers-10-114000653.html\" rel=\"nofollow ugc noopener\">offered every household in Hazle Township $10,000</a> if its campus gets approved, which some residents (perhaps correctly) called a bribe.</li></ul>\n<p>I would not be surprised to see hyperscalers covering a whole town’s power bills as part of hosting a local campus. Most states, <a href=\"https://texas.public.law/statutes/tex._util._code_section_36.003\" rel=\"nofollow ugc noopener\">Texas included</a>, don’t let a utility single out one town, but at a small utility where data centers use most of the power, like <a href=\"https://www.cobank.com/knowledge-exchange/earning-the-business-by-demonstrating-network-value\" rel=\"nofollow ugc noopener\">Oregon’s Umatilla Electric</a>, covering a <a href=\"https://www.eia.gov/electricity/sales_revenue_price/pdf/table_5A.pdf\" rel=\"nofollow ugc noopener\">typical household’s</a> bill for each of its <a href=\"https://www.umatillaelectric.com/about-us/who-we-are/\" rel=\"nofollow ugc noopener\">roughly 17,000 meters</a> would only cost about $30 million a year. Such an agreement could pencil because that’s less than 0.5% of what a 1 GW campus <a href=\"https://epoch.ai/data-insights/ai-datacenter-cost-breakdown\" rel=\"nofollow ugc noopener\">costs to own and run</a>.</p>\n<p>It’s also important to read the fine print when deals are made. In Arkansas, Google agreed to pay <a href=\"https://www.arkansasonline.com/news/2026/sep/03/googles-contribution-was-at-issue-in-arkansas/\" rel=\"nofollow ugc noopener\">$443 million</a> up front toward an Entergy solar plant for its data center. The catch is that Entergy counted it as <a href=\"https://www.arkansasonline.com/news/2026/sep/03/googles-contribution-was-at-issue-in-arkansas/\" rel=\"nofollow ugc noopener\">prepayment for power</a>, so it can still seek the plant’s full cost plus a return from all its customers. And Entergy <a href=\"https://www.cnbc.com/2026/09/02/google-data-center-arkansas-entergy-court.html\" rel=\"nofollow ugc noopener\">sued two newspapers</a> to stop them from reporting on the contract, then dropped the suit after a judge refused. Even if the deal is legal, this isn’t how you build trust with the community.</p>\n<p>A campus that levels with its neighbors and actually follows through keeps people on its side, and the next one gets easier to welcome. Get that wrong and everyone else can end up paying for it. In PJM, <a href=\"https://www.utilitydive.com/news/pjm-data-centers-capacity-auction-imm-bowring/825626/\" rel=\"nofollow ugc noopener\">the market monitor says data centers account for 38% of the latest capacity bill</a>, some $6.3 billion. Let me be clear: none of that justifies a blanket pause. But it does mean getting the rules and incentives right as we scale up development. AI companies have <a href=\"https://www.powermag.com/hyperscalers-sign-white-house-pledge-to-fund-data-center-power-grid-upgrades/\" rel=\"nofollow ugc noopener\">pledged to pay their way</a>, and most would rather connect to the grid than avoid it. It seems ideal for everyone that we let them do so instead of driving that spending into private islands, or pushing infrastructure upgrades that we’ll need anyway onto everyone else’s bills.</p>\n<p>Texas created the energy fast lane first; now it has the opportunity to show us a better one, and I expect it will. Power is where America finds out whether it can still build.</p>\n<p>If you’re working on energy problems, I’d love to learn from you.</p>","headings":[{"level":3,"text":"What connecting to the grid actually means","id":"what-connecting-to-the-grid-actually-means"},{"level":3,"text":"What bringing your own power solves","id":"what-bringing-your-own-power-solves"},{"level":3,"text":"What flexibility can buy","id":"what-flexibility-can-buy"},{"level":3,"text":"Getting to hundreds of gigawatts","id":"getting-to-hundreds-of-gigawatts"},{"level":3,"text":"After the pause","id":"after-the-pause"}]}}